BEFORE THE VIDYUT OMBUDSMAN
Present
K.Rajagopala
Reddy, Director (Law) and
Vidyut
Ombudsman
Dated: 10-04-2008
M/s. Sai Rayalaseema
Paper Mills Ltd
Plot No. 6, H.No.
6-3-569/1/4,
2nd Floor,
Rockdale Compound,
Opp : RTA Office,
Somajiguda, Hyderabad … Appellant
1. The
Superintending Engineer/Operation/APCPDCL/ Kurnool Circle
2.
The Chief General Manager/Commercial/
APCPDCL / Corp. Ofice / Hyd
3. The
General Manager/Revenue/ APCPDCL / Corp. Office / Hyd
4. The General Manager/Customer Services/
APCPDCL / Corp. Office / Hyd
… Respondents
The appeal /
representation dated 26.11.2007 (received on 26.11.2007) of the appellant has
come up for final hearing before the Vidyut Ombudsman on 27.03.2008 in the
presence of Sri. B.V.Sathya Sai Prasad, Chairman and Managing Director on
behalf of the appellant, no representation on the behalf of the respondents and
having stood over for consideration till this day, the Vidyut Ombudsman passed
/ issued the following:
Aggrieved by
the order passed by the Forum for Redressal of Consumer Grievances of APCPDCL
(for short the “Forum”) in C.G. No. 28 / 2007-08 / Kurnool Circle dated
16.11.2007, the appellant herein filed appeal / representation dated 26.11.2007
mentioned supra, stating that: -
(a) the
paper mill of the appellant was closed
in the year 1989 as it became a sick company. The appellant company was
referred to BIFR for suitable rehabilitation.
However, the company was reopened again in the year 2006 with certain
reliefs and concessions granted by different departments including the Central
Power Distribution Company of Andhra Pradesh Limited (for short “APCPDCL”).
(b) at the time
of reopening, the appellant intended to avail CMD of 11000 kVA in a phased
manner with 6000 kVA in the first phase and the balance 5000 kVA in the second
phase after about six months.
(c ) however, due
to unprecedented floods and for want of funds, the appellant could not complete
expected works and therefore, its demand remained 6000 kVA only. In view of the above, the appellant during
the years 2006 and 2007 submitted several letters requesting APCPDCL to defer
release the additional demand of 5000 kVA. APCPDCL did not release additional
demand till June 2007. However,
suddenly from the month of July 2007 onwards, APCPDCL issued revised bills for
11000 kVA with effect from f April
2007. In the months of July and August, 2007 the appellant was denied incentive
as the demand was calculated at 1000 kVA. The appellant was not informed at any
point of time that additional demand of 5000KVA was released. The action of the APCPDCL in calculating the
demand including additional demand of 5000 kVA, which is not consumed, is a heavy
financial burden to the appellant which is already a sick industry and under
rehabilitation.
(d) aggrieved by
such action of APCPDCL, the appellant by letter dated 11.10.2007 referred its
grievance to the Forum. However, the
Forum without giving any opportunity to present the case of the appellant and
without holding any hearing, disposed-off the case by an order 16.11.2007 ,
without addressing the grievance of the appellant. Hence, the appeal / representation dated 26.11.2007 as mentioned
supra.
2. In terms of
Clauses 8(1)(c) and 11 (1) of the APERC Establishment of Forum and Vidyut
Ombudsman for Redressal of Grievances of Consumers Regulation, 2004 (for short
“Regulation No. 1 of 2004”), the Vidyut Ombudsman
is required to promote settlement by mutual agreement between the parties. In pursuance of the same, respondents were
intimated of the filing of the appeal / representation by notice dated
27.11.2007.
3. By Lr No.
SE(O)KNL / SAO / JAO / F.097 / 544 / 07 dated 27.12.2007, respondent No.1
submitted that respondent No. 2 informed him that the Board of Directors of
APCPDCL on 29.11.2007 resolved that (i) the release of second phase demand of
5000 kVA to the appellant be postponed upto June 2008 (ii) the C.C. bills for
the period from April to October 2007 be revised treating the CMD of the
appellant as 6000 kVA, instead of 11000 kVA (iii) to withdraw the excess demand
charges billed against the second phase demand of 5000 kVA and (iv) to allow
the eligible incentive amount.
Respondent No.1 further informed that in pursuance of the said resolution
(i) excess demand raised along with surcharges was withdrawn by allowing
incentives from April to October 2007 (ii) the incentive amount of
Rs.3,14,876.80 ps was already allowed for the month of June 2007 and (iii) the
incentive for the month of August 2007 is allowed and the same was adjusted in
the C.C bill of December 2007 payable in January 2008. Lastly, it is submitted that CMD of the
appellant of HT service is 6000 kVA.
4. By letter
dated 03.01.2008, the Vidyut Ombudsman requested the appellant to confirm the
information submitted by respondent No.1 in his letter dated 27.12.2007
referred to above and to state whether such information redresses the grievance
of the appellant. A copy of the letter dated 27.12.2007 of the respondent No.1
was also forwarded to the appellant. In response, the appellant sent a reply
dated 14.01.2008 stating that the APCPDCL granted relief of postponing the
release of second phase of 5000 kVA upto the month of June 2008 and revising
the bills for the period from April to October 2007. It is further stated that
the appellant is satisfied to that extent.
However, it is submitted by the appellant that while formulating
rehabilitation scheme, the Appellate Authority for Industrial & Financial
Reconstruction (for short, “AAIFR”) envisaged certain concessions, viz., (i) to
accept 25% down payment of Rs.65 lakhs
of actual consumption charges after waiver of minimum demand /
consumption charges, (ii) to retain the existing consumption deposit of
Rs.84,27,000/- against power supply to the company without demanding for
additional consumption charges, (iii) to restrict power cut, if any, to 25% for
at least 3 years from the date of reopening of the plant and (iv) to fix
requirement of power of minimum demand as may be required by the company. It is requested to grant the above mentioned
reliefs and to direct APCPDCL to adhere the above mentioned terms.
5. On 23.01.2008, a copy of the above mentioned letter dated 14.01.2008 was forwarded to respondent No.1 with a request to offer its comments on the submissions made by the appellant therein. In response, respondent No.1 sent Lr.No. SE(O)KNL / SAO / JAO / F.097 / D.No. 643 / 07-08 dated 18.02.2008 stating that the Govt. of Andhra Pradesh issued G.O.Ms.No.144 dated 18-05-2006 extending certain concessions to the appellant and in accordance with the same APCPDCL agreed to restore power supply to the appellant in a phased manner subject to certain conditions. In pursuance of the same APCPDCL and the appellant entered Memorandum of Understanding on 28.08.2006. It is further stated that a demand notice was issued to the appellant for payment of Rs.3,08,06,460/- in 36 installments vide Lr No. SE(O)KNL / SAO / JAO / HT,Rev/ D.No. 275 / 07 dated 13.07.2007. However, the appellant filed W.P.No.17968 /2007 before the Hon’ble High Court of Andhra Pradesh on 23.08.25007 granted interim order stating “pending further orders there shall be interim suspension as prayed for a period of one week” and on 28.08.2007 the said Court issued further orders stating that “earlier orders shall continue until further orders”.
6. On
20.02.2008, a copy of the letter dated 18.02.2008 referred to above was
forwarded to the appellant with a request to offer its comments on the
information submitted by respondent No.1. In response, the appellant forwarded
a copy of its letter dated 15.02.2008 submitted to the Chairman and Managing
Director of APCPDCL, which clarifies its position and for settlement of the
matter.
7. Notice
of hearing scheduled on 27.03.2008 was sent to the appellant as well as to
respondent No. 1. On the said date of hearing, heard the Chairman &
Managing Director of the appellant and there is no representation on behalf of
respondent No.1. On 04.04.08 “written arguments” was submitted on behalf of the
appellant, wherein it is requested to
(i) direct APCPDCL to defer the availment of 5000 kVA (second phase)
demand till it is required by the appellant instead of June 2008 as already
agreed by APCPDCL, in addition to reiterating the other two demands viz., (ii)
to waive the minimum demand and other penal charges in terms of rehabilitation
scheme sanctioned by BIFR / AAIFR and (iii) not to charge interest on deferred
payment of monthly installments being paid towards Rs.65 lakhs arrears of the
actual consumption charges pertaining to the closure period.
8. The
point that arises for consideration is “whether the appellant is entitled for
the relief as claimed by it in its appeal / representation dated 26.11.2007”.
9. In this
context, it is necessary to refer to the letter dated 11.10.2007 filed by Sri K.S.R.Murthy, Director of
the appellant company before the chairperson of the Forum. As per the said letter / complaint, the
grievance of the appellant is that the “action of the APTRANSCO (should have
been APCPDCL) in levying charges for the 5000 kVA demand which is not being
drawn and utilized is causing lot of hardship to the company. Besides, the
authorities are threatening to disconnect power supply in case they do not pay
minimum demand charges for the undrawn and unutilized demand”.
10. The Forum
below framed two issues viz., (i) whether the demand raised from 4/07 onwards
for the phased demand of 5000 kVA aggregating to 11000 kVA by the respondents
is in order ? and (ii) are there any short comings on the part of
respondents. After enquiry, the Forum
came to the conclusion that as per Clause 7 of the HT Agreement executed by the
appellant and as per Clause 5.9.4.3 of General Terms & Conditions of Supply
and Tariff in force, the demand raised by the respondents for 11000 kVA CMD
after expiry of six months period from the date of execution of Agreement on
28.09.2006 is in order. For the said
reason, the Forum in its order dated 16.11.2007 came to the conclusion that
there is no deficiency of the service on the part of the respondents.
11. In the appeal
/ representation dated 26.11.2007 the appellant represented that the Forum
disposed off its complaint without giving an opportunity to present its case
and without holding any hearing.
Whatever it might be, respondent No.1 by his letter dated 27.12.2007
brought to the notice of the Vidyut Ombudsman the resolution passed by Board of
Directors, APCPDCL on 29.11.2007 as stated in paragraph 3 supra, as seen from
the said letter dated 27.12.2007, the grievance of the appellant raised before
the Forum was redressed in totality. By letter dated 14.01.2008, the appellant
also confirmed that it is satisfied with the relief of postponing of release of
second phase of 5000 kVA up to the month of June 2008 and revision of bills for
the period from April to October 2007.
However, the appellant is seeking relief with regard to certain other
related issues which were not agitated before the Forum. As an Appellate Authority, the scope of appeal
/ representation before the Ombudsman is limited to the extent whether the
order passed by the Forum below is correct or not. In this case, the relief sought by the appellant before the Forum
was subsequently granted by APCPDCL and therefore the Ombudsman is not
necessitated to examine whether the order of the Forum is correct or not.
12. As an
Appellate Authority, the Ombudsman cannot traverse beyond the complaint
agitated before the Forum below and grant relief which was not subject matter
before such Forum. Even in the appeal / representation dated 26.11.2007, the
appellant has not mentioned about waiver of minimum demand charges and other
charges for the closure period from 1989 onwards and not to insist for the
additional consumption deposit atleast for next three months, etc. After informing the decision of Board of
Director of APCPDCL by the respondent No.1 in his letter dated 27.12.2007 which
was communicated to the appellant by the Ombudsman by notice dated 03.01.2008,
the appellant for the first time brought on record the rehabilitation scheme of
AAIFR and sought for directions to APCPDCL for implementation of concessions
supposed to have been envisaged in its order dated 20.07.2005. As mentioned
above, the appellant cannot be permitted to bring new issues on record which
were not agitated before the Forum. For that reason, the Vidyut Ombudsman
cannot direct APCPDCL to defer the availment of 5000 kVA (second phase) demand
till it is required by the appellant instead of June 2008, as requested by the
appellant in its “written arguments” filed on 04.04.08. Thus, the appeal /
representation dated 26.11.2007 is devoid of merits.
13. However, the
appellant is at liberty to raise its grievances related to Modified
Rehabilitation scheme dated 20.07.2005 which were agitated for the first time
in the proceedings before the Vidyut Ombudsman and as already brought to the
notice of Chairman & Managing Director in its letter dated 15.02.2008 with
APCPDCL. In view of the fact that the
appellant is a sick industry and under rehabilitation, it is necessary for
APCPDCL to resolve the grievances of the appellant and to grant reliefs and
concessions for its revival as per the recommendations of State Investment
Promotion Board meeting held on 13.12.2005, order of AAIFR dated 20.07.2005 and
G.O.Ms.No.144, Industries & Commerce (IFR.I) department dated 18.05.2006 in
totality. Further, in view of the
policy of the government to encourage industries to have more growth, the
specific request of the appellant to waive minimum demand charges and other
charges for the closure period from 1989 onwards and not to insist for
additional consumption deposit atleast for next three years as per the terms of
rehabilitation scheme mentioned in the letter dated 15.02.2008 referred to
above needs to be considered expeditiously by APCPDCL.
14. In this
context, it is necessary to state that in the year 2001, Chairman and Managing
Director, APTRANSCO addressed Lr.No.CE/Comml/AE/TCS /D.No.411/ 2001 dt : 29-05-2001 to the
Secretary, APERC relating to HT Industrial sales promotion and rationalization
of procedures in respect of collection of minimum charges during periods of
long closure of industrial units due to sickness. As a part of intensive power marketing strategies, APTRANSCO made
certain proposals for HT industrial units which are under disconnection and are
closed for long periods. Thereafter, the Secretary, APERC by
Lr.No.APERC/Secy/Dir-Tariff/F./ D.No.4966/ 2001, dt: 05-11-2001 communicated
approval of the scheme proposed by APTRANSCO as above with a condition that
such scheme should be made applicable to HT-I consumer units under
disconnection for more than four months and the said scheme was valid till
31.10.2002. The scheme was further extended from time to time, upto 31.03.2005.
Subsequently by another letter dated 25.05.2005, the Secretary communicated
further extension of the scheme upto 31.03.2006 and application of such reliefs
to industrial units under LT Cat III(A) and III (B) as well. In order to
develop HT & LT industrial sales and to increase revenues, DISCOMs gave
wide publicity to the said scheme approved by the Commission. By letter No. CGM / (Coml) / SE(C) / DE (C)
/ ADE-II / F.No. Indl Sales/07 D.NO. 1995 Dt. 29.03.2008, the Chief General
Manager / Comml / APCPDCL requested the Commission to extend the relief to the
sick industries under LT Cat-III (A), III (B) and HT Cat-I upto 31.03.2009 for
promoting industrial sales..
15. For all the
reasons mentioned above, the appeal / representation dated 26.11.2007 is
dismissed, however, with a direction to
APCPDCL to redress grievances of the appellant related to Modified
Rehabilitation scheme dated 20.07.2005, especially the request of the appellant
to waive minimum demand charges and other charges for the closure period from
1989 onwards and not to insist for additional consumption deposit atleast for
next three years as per the terms of the said rehabilitation scheme,
expeditiously to encourage the appellant to revive its unit.
This order is corrected and signed on this 10th
day of April 2008.