BEFORE THE VIDYUT OMBUDSMAN
5th Floor, Singareni Bhavan, Red Hills,
Present
S. Surya Prakasa Rao,
Vidyut Ombudsman
Dated 29-03-2006
Appeal No 1 of 2006
M/s. Madras Cements Ltd.,
Kumara Swamy, Raja Nagar,
Jaggayapet Taluk,
Krishna District.
(Represented
by Senior Manager, Electrical) ...….
Appellant
and
1. The Director (Comml.
& Proj), APSPDCL,
Tirupati
2. The Superintending
Engineer (Operation), APSPDCL
3. The Chief Engineer (O
& M), APSPDCL,
..….. Respondents
This is an appeal dt. 28-12-05 filed by M/s. Madras
Cements Ltd., a HT consumer (hereinafter called the appellant or appellant
consumer) coming up for hearing by Vidyut Ombudsman pursuant to an order of the
Forum for redressal of grievances of consumers of SPDCL, Tirupati (hereinafter
called the FORUM) dt. 13-12-05 in C.G.No.35 of 2005, and having stood over till
this day the Ombudsman issues the following:
2. This
appeal dated 28-12-05 is received in the office of the Ombudsman on
30-12-05. The brief facts of this matter
are as follows:
The appellant consumer M/s. Madras
Cements availed power supply from the erstwhile APSEB at 132kV for a contracted
demand of 16500 kVA, which was reported to have been released in 3 stages; 2000
kVA on 24-12-85, 12,000 kVA, on
24-10-86, and another 2500 kVA (total 16.5 MVA) on 22-9-87, for their cement
factory at Jaggayapet,, Krishna Dist. They paid all the required charges in
December 1985 for release of supply as per APSEB Rules & Regulations. They have gone for dedicated line at their
cost in 1995 from Chillakallu Sub-Station (near Jaggayapet,) due to
disturbances in the 132 kV common feeder.
In June 1998, they have de-rated their contracted demand from 16,500 kVA
to 7500 kVA. Later due to increase in
the operating cost of captive power plant, they requested the SPDCL in
September 2005 for release of additional demand of 5200 KVA over the existing
demand of 7500 KVA. The appellant also
requested SPDCL in Lr. dated 25-9-05 to waive the Development charges, as no
additional expenditure is involved for release of the additional demand. The respondent SPDCL did not agree for this
request as the consumer did not pay the Development charges even at the time of
release of supply in 1985 and requested the consumer in Lr. dated 27-9-05 to
pay the Development charges for release of supply for the additional
demand. The consumer paid Rs.39 lakhs
towards development charges and availed supply for the additional demand of
5200 kVA on 10-10-05. After availing the
supply for the additional demand, duly paying the development charges as
insisted by the SPDCL, the appellant consumer approached the grievance cell of SPDCL
(Forum) in letter dated 22-11-05 with a request to consider waival of
Development charges of Rs.39 lakhs paid by them and adjust in future CC
bills. The Forum of SPDCL in its order
dated13-12-05 held that the collection of the Development charges by SPDCL is
in order.
3. In
the appeal dated 28-12-05, the appellant mainly raised the following
contentions:
(i)
All charges
payable as per the APSEB rules and regulations were paid before release of
supply in 1985.
(ii)
The restoration
of the Demand of 5200 KVA was done on existing available infrastructure without
any expenditure.
(iii)
The Order dated
13-12-05 of FORUM contains a reference to communication of APPCC dt.16-11-05,
which states that those industrial consumers who want to restore their earlier
derated Contracted Maximum Demand (CMD), do not require to pay development
charges as infrastructure to meet their earlier CMD had already been
created. Though they requested SPDCL by
25-9-05, their request was not considered in the above order of APPCC.
The appellant requested for waival of the Development
charges on the above grounds.
4. In
the counter filed by the respondent SPDCL i.e., SE/Opn/VJA in his Lr. dated
30-1-06 and Dir (projects) in his Lr. dt. 27-01-06, the following points are
made:
(i)
The APTRANSCO
order TOO (Comml.) Ms. No. 52 dt
29-05-2001, which provides for waival of Development charges for restoration of
earlier derated demand, is applicable only for those who paid development
charges earlier.
(ii)
The appellant
had not paid development charges at the time of release of supply in 1985 and
hence they are not entitled for the relief provided in TOO (Comml.) Ms. No. 52
dtd: 29-5-01.
(iii)
The appellant
paid the Development charges for the additional demand of 5200 KVA now
requisitioned, prior to the APPCC Order dated 15-11-05 and hence this exemption
does not apply to the appellant consumer.
(iv)
SPDCL feels that
waival of development charges is not a grievance as per citizen charter to
represent to grievance cell.
(v)
The contention
of the appellant that the additional demand was released on the existing infrastructure
without any expenditure is not correct as several improvement works were taken
up to afford quality of power to all the consumers.
(vi)
The SE/O/VJA,
the second respondent, has furnished in his counter dated 30-01-06, the list of
development works executed in and around Chillakallu substation where the
additional demand is incident.
Relying on the above grounds, the respondent SPDCL
refused to refund the Development Charges already paid by the appellant
consumer for the additional demand of 5200 kVA released on 10-10-05.
5. In
view of the above facts on record and rival contentions of the parties here in,
the points for consideration are:
(a) Whether the appellant is required to pay development
charges for the additional demand of 5200 kVA requisitioned in September 2005?
(b) Whether the appellant is entitled for refund of the
development charges of Rs.39 lakhs paid on 10-10-05, in view of the APPCC
letter dt.16-11-05?
6. As
required under clause 8(1) (c) of the APERC Regulation No.1 of 2004, the parties
here in were advised by the notice dated 03-01-06, to reach a mutually
acceptable settlement and submit the document of settlement reached if any to
the Ombudsman in person in the meeting convened on 23-01-05. The representative of appellant appeared
before the Ombudsman on 23-01-05 and informed that no settlement was
reached. No representative of the
respondent SPDCL appeared on 23-01-05.
Later the respondent No.1 and 2 filed counters in compliance with the
notice dated 03-01-06. The Ombudsman
heard the parties here in on 27-03-06.
Sri K.Veerabhadra Rao, Senior Manager Electrical, represented the
appellant while Sri B.Suri Babu, DE (Commercial) SPDCL represented the
respondents, during the hearing.
7. The
rival contentions are examined here under:
The appellant consumer merely sought
waival of development charges on the sole ground that no additional expenditure
is involved in release of the additional demand and that all the required
charges for release of supply for a demand of 16,500 kVA were already paid in
1985 as per APSEB rules and regulations.
The appellant consumer did not quote the T.O.O Ms. No. 52 dated 29-05-01
of APTRANSCO either in his letter dt. 25-9-05 addressed to MD/SPDCL or in his letter
dt. 22-11-05 addressed to the Secretary of consumer Grievance Cell (FORUM) of
SPDCL. In this appeal the appellant
merely quoted the relevant extract from the Order dt 13-12-05 of the Forum of
SPDCL containing reference to the Lr. dt. 16-11-05 of APPCC.
The
respondent SPDCL quoted the provisions of TOO Ms. No. 52 dt. 29-5-01and the APPCC letter dated
16-11-05 in its counter before the FORUM.
The respondent SPDCL relied on the interpretation of TOO No. 52 dated
29-5-01 and APPCC lr. dated 16-11-05 even in its counter on this appeal. Sri B.Suri Babu, the DE (Commercial), SPDCL
produced a copy of the lr dt. 26-02-05, from Director (Projects), SPDCL
addressed to CGM (Comml & RAC),
CPDCL where in the decision of SPDCL to collect Development charges in respect
of consumers who have not earlier paid the same, was informed to CPDCL.
The
proper course of examining this matter would, perhaps, be from the view point
of the enabling power or authority of the respondent SPDCL to collect the
Development charges in September 2005 when the appellant sought release of
additional demand. When this question of
the authority for collection of Development charges was put to Sri B.Suri Babu
representative of SPDCL, during the hearing held on 27-03-06, he said the authority
was the Order dt. 24-08-05 of the APERC on the collection of development
charges communicated to the DISCOMs the in the Lr. dated 29-8-05 of the
Secretary, APERC. He said that the
development charges were collected @ Rs 750 KVA as per Annexure II to the said
Order of the APERC. I have gone through
the said Order of the Hon’ble Commission. The provisions of TOO Ms. No. 52 dt.
29-05-01 was not a matter for consideration and was not dealt in the said
proceedings. In the absence of any
proposals by the Licensees in the above proceedings and no decision of the
Hon’ble Commission thereon, it is difficult to infer whether the earlier order
of TRANSCO i.e. T.O.O. Ms. No. 52 dt. 29-05-01 has any statutory or Regulatory
sanction for enforcement. Hence I am not
inclined to interpret the provisions of either TOO Ms. No. 52 dated 29-05-01 or
APPCC Lr dt. 16-11-05. Suffice to say
that I am convinced with the reply of Sri B.Suri Babu, the representative of
the respondent SPDCL during the hearing held on 27-3-06, that the SPDCL
collected the development charges at the rates mentioned in the Annexure II of
the Commission’s Order dt.24-08-05 and accordingly I hold that the SPDCL is
entitled to collect development charges from the appellant for the additional
demand of 5200 kVA released in October 2005.
Regarding the nature of complaints to be represented
to the FORUM, I am unable to agree with the contention of Director (Projects),
SPDCL that waival of Development charges is not a grievance as per citizen
charter to represent to the grievance cell.
It is made clear that any consumer is entitled to approach the FORUM on
any grievance, not necessarily listed in the citizens charter and the FORUM is
expected to handle the complaints in accordance with the provisions under
sub-clauses 7 to 11 of clause 5 of the APERC regulation No.1 of 2004.
Having referred to the order dt. 24-08-05 of the
Hon’ble Commission, I also advise the respondent SPDCL to file relevant data as
directed in para 14 of the said order if not already done, to facilitate issue
of fresh regulation by the Hon’ble Commission in the matter of recovery of
expenses by Distribution Licensees u/s 46 of the Act towards providing electric
line / electrical plant for giving supply pursuant to application u/s 43 of the
Electricity Act 2003.
This order is
signed and issued on 29th day of March, 2006