VIDYUT OMBUDSMAN
5th
Floor, Singareni Bhavan, Red Hills,
Present: S. Surya Prakasa Rao, Ombudsman
Appeal No 22 of 2006
Sri
P.Srinivasa Reddy
Plot
No.402
1/14
Brody Pet
……. Appellant
And
1. Assistant
Engineer / Operation / D 1 /
2.
Assistant Divisional Engineer / Operation / Town II /
3.
Divisional Engineer / Operation / Town /
4.
Superintending Engineer / Operation /
This
representation dated
ORDER
2. The facts on
record in this appeal are briefly mentioned herein. The power supply to the premises bearing Flat
No. 402,
3. In his appeal
the appellant made the following prime contentions:
(i)
They are using only less than 1 KW load against the
sanctioned load of 5 KW and the meter got burnt with in 40 days of release of supply.
(ii)
The observation of the learned chairperson of the Forum
about shifting of fan and T.V. from the Hall are not true
(iii)
If there was fault in wiring, the T.V and fan also would
have burnt.
(iv)
The respondents cannot establish the defect in wiring
without megger test.
(v)
The respondents have deceived the consumer by showing his
installation as defective and by demanding payment of cost of meter.
For the reasons stated above, the appellant wanted justice
to be done by Ombudsman.
4. As per clause 8(1) (c) of the Regulation No.1 of 2004 of the
Hon’ble APERC, the Ombudsman is required in the first instance, to endeavor to
arrive at a settlement by mutual agreement. Accordingly by notice dated
5. As no settlement was reached, the SE/Operation/Guntur
(respondent No.4) filed the counter in his letter dated
(i)
The DE/DPE/Guntur inspected the service on
(ii)
As per clause 7.5.2 of the General Terms and Conditions of
Supply (GTCS) the consumer has to pay cost of meter if the cause of burning of
meter is attributable to consumer
(iii)
The causes attributable to the licensee are; high voltage,
loose contacts, and aging of meter which do not apply in this case.
(iv)
The causes attributable to the consumer are: Meter getting
wet, defects in installation, un-authorized additional load etc.
(v)
The cause for burning in this case is defect in internal
wiring of consumer’s installation.
(vi)
Hence the cost of meter is collected as per the GTCS.
The SE/Operation/Guntur has also enclosed copies of the
following documents:
(a)
Test Report dated
(b)
Extracts of the pages of FOC register in which the complaint
of the consumer on
(c)
Copy of the Inspection report of DE/DPE/Guntur on the
inspection of this service on
(d)
Meter charge slip dated
(e)
Report dated
(f)
Copy of order dated
6. In the
notice issued on
7. During
the hearing on
8. On
behalf of the respondents Sri. V. Rajasekhar SE/Operation/Guntur re-iterated
the points made in the written submission (counter) and asserted that consumer
has to bear the cost of meter, as there is no deficiency attributable to the
licensee. Regarding the consumer’s contention that the installation is to be
tested before release of supply, the respondent No.1 stated that they are not
bound to test it. He further stated that in this case the installation was
inspected by the Electrical Inspector as the height of the apartment is above
15 Mts.
9. In the
background of the above rival contentions, the issues for consideration in this
appeal are:
(i)
Whether the
licensees have established the cause for the burning of meter
(ii)
If so whether
they are attributable to the consumer or licensee
(iii)
Whether the licensee
is entitled to demand payment of cost of the burnt meter in this case?
10. The
material on record in this appeal does not reveal any document, which
establishes the cause of burning of meter. Neither the Inspection report dated
I am not inclined to accept this
reasoning of the respondents.
11. I
made the following enquiries during the hearing.
(a) What
is status (condition) of the cutout, which is expected to isolate the
consumer’s installation from the licensee’s system if the fault is on account
of defect in consumer’s installation?
(b) Why
they have not tested consumer installation before release of supply as required
under clause 5.7 of the GTCS approved by the Hon’ble Commission?
12.
(a)
Condition of Cut-out:
In reply to (a) the respondents
have stated that the cutout was O.K, but the fuse has blown. On an observation from me about
providing the conventional cutout and fuse instead of MCB, the respondents have
stated that MCB are not being used as they are frequently malfunctioning.
Assuming that the consumer’s installation is defective, the fuse in the cutout
should have blown before any equipment is burnt on the downstream side or
before damage is caused to the meter and the Licensees system on upstream side.
If the electronic meters are so sensitive and get burnt due to faults on the
load side before the fuse in the cut-out blows off, it is imperative that
licensee has to provide better protection devices like MCBs.
(b) Testing of installation:
Regarding the requirement of testing the
installation, the respondents have stated that in respect of the apartments
which are above 15 meters height, the installations have to be inspected by the
Electrical Inspector as per IE Rules and hence they need not test the
installations before release of supply for such installations. I asked the respondents to provide a copy of
the approval accorded by the Electrical Inspector for the installations of this
apartment. It is still awaited. Be that as it may, I am of the view that the
requirement of inspection by the Electrical Inspector and his approval does not
absolve the licensee from discharging its duties as per the Licence conditions
or as per the General Terms and Conditions of Supply approved by the
Commission. The inspection and approval of a statutory authority like
Electrical Inspector is from the viewpoint of public safety, where as the
provisions in the GTCS are a duty as well as obligation of the licensee towards
individual consumer.
The clause 5.7 of GTCS, which is relevant for this
discussion, is extracted hereunder:
“5.7 Inspection
and Testing of consumer Installation
5.7.1 Inspection
and testing of the LT consumer installation
5.7.1.1 Upon receipt of the Wiring
Completion Report under clause 5.6, the Company will, notify the consumer as
and when the Company's representative proposes to inspect and test the
installation. It shall then be the duty
of the consumer to arrange for a representative of the licensed electrical
contractor technically qualified and employed by him, to be present at the
inspection to give the Company's representative any information required by him
concerning the inspection.
5.7.1.2 No connection shall be given until the consumer's
Installation has been inspected and tested by the Company and found
satisfactory. No charge shall be made
for the first test by the Company but subsequent tests due to faults found at
the initial test or failure of the contractor's representative to keep the
appointment shall be charged for in accordance with the miscellaneous and
general charges in force from time to time. The Company does not accept
responsibility with regard to the maintenance or testing of wiring on the
consumer's premises.
5.7.1.3 Before taking the insulation test of the installation
wiring must be completed in every aspect.
All fittings such as lamps, fans, cookers, motors etc., must be
connected up, fuses inserted and all switches closed before the tests are
carried out. Temporary wires or fittings
or dead ends should not be included in the installation and no part of the work
should be left incomplete. The
insulation resistance of the entire installation to earth shall be tested from
the installation side of the Company's terminals.
5.7.1.4 The Company shall not connect the conductors and fittings
on the consumer's premises with its works unless it is reasonably satisfied
that the connection will not at the time of making connection cause a leakage
from those conductors and fittings exceeding one-five thousandth part of the
maximum supply demand on the consumer's premises.”
I therefore do not agree with the contention of the
respondents that they are not required to for test the installation before
release of supply. How ever it is to be noted that mere testing at the time of
release of supply does not absolve the consumer from the liability on account
of the defects that may set in later in his installation.
13. A new
evidence was sought to be the putforth by the respondents during the hearing by
stating that the incoming wires to cutout are having different colour as the
old wires were burnt due to fault in consumer installation. Assuming that it is
true, it only confirms the in-effectiveness of the protection expected from the
fuse provided in the cutout. Either the fuse was not correct
size and quality or the fault would have generated upstream side of the
cutout if the fuse provided is of correct specification. The consumer cannot be held responsible un-less there is evidence of his interference with
licensee’s equipment, which was not established in this case.
14. Regarding
the observation of the learned Forum that the meter got burnt due to defect in
installation of consumer, I am of the view that the evidence relied upon by it
is not sufficient to establish the defect.
Not even a trace of evidence of damage in the entire installation of
consumer was established in various inspection of the
respondents. Even the evidence brought in by respondents during hearing about
the wires between meter and cutout, they belong to the licensee only. In my
view, in the cases where the defect cannot be conclusively established, the
benefit of doubt should always be given in favor of the consumer. I am
therefore not able to endorse the decision of the learned Forum in this appeal
15. Concluding
the above discussion I decided the following award in this appeal
i.
The licensee is
not entitled to collect the cost of burnt meter in this case, since the cause
of burning of meter has not been established as required in the Regulation of
the Hon’ble Commission and as per the award earlier given by this Ombudsman in
Appeal No.3 of 2005.
ii.
Hence the amount
of Rs.1500/- paid by the consumer shall be refunded by adjustment in future
C.C. bills till it is fully exhausted.
16. The
appellant is required to communicate his acceptance for this award in full and
final settlement of his claim, to the respondent No.2 with in 15 days from the
date of receipt of this Order. The licensee is required to implement this award
only after the appellant gives his acceptance for this award in full settlement
of his claim in the appeal as per clause 12 of the Regulation No.1 of 2004.
17. Reasons for delay:
This
appeal was received on
VIDYUT OMBUDSMAN