V I D Y U T    O M B U D S M A N

Office of ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

5th Floor, Singareni Bhavan, Red Hills,

Hyderabad – 500 004

 

Dated: 20-02-2007

 

Present: S. Surya Prakasa Rao, Ombudsman

 

 

Appeal No 30 of 2006

 

 

 

Between

 

Sridevi Hatchery,

SC No. 2107000318,

Bharthipudy,

Bapatla Mandal,

Guntur District                                                                                                                      …….        Appellant

 

 

and

 

 

1.     Additional Assistant Engineer / Operation / Rural / Bapatla

2.     Assistant Divisional Engineer / Operation / Bapatla

3.     Assistant Accounts Officer / Electricity Revenue Office / Bapatla

4.     Divisional Electrical Engineer / Operation / Tenali                                                          …….         Respondents

 

 

           This representation dated 18-10-2006 (received on 14-11-2006), referring to the appeal dated 04-03-2006 (which was not received in the office of the Ombudsman) made by the Managing Partner, Sridevi Hatchery, Bapatla (hereinafter called as consumer or appellant) against the order dated 06-03-2006 of the Forum for redressal of grievances of consumers (hereinafter called the Forum or CGRF) SPDCL, Tirupathi in CG No. 62  / 05-06, Guntur circle, coming up for consideration before the Ombudsman and having stood over till this day, the Ombudsman issues the following

 

  

ORDER

 

2.        The facts on record in this case are briefly narrated herein.  The consumer is availing supply for their hatchery under LT industrial category with SC No. 318 of Bharthipudi.  For the month of September 2005, he received an abnormal bill for Rs. 53,662 for a consumption of 13, 695 units.  The consumer made representation to the respondent No.1 on 30-10-2006, which was rejected by him in his letter dated: 28-12-2006.  The consumer then approached the Forum of SPDCL on 06-02-2006 requesting for revision of the bill.  The learned Forum confirmed that the bill issued is in order and requires no revision.  Hence the appeal.

 

3.        In his appeal the consumer made the following prime contentions:

a.     The Hatchery is meant for production of scampi shrimp with a connected load of 29.99 HP, out of which two rotor blowers of 7.5 HP (2 x 7.5 HP) are used for aeration of the water tanks and another 13 HP for pumping and clearing of water.  Balance load is for lighting.

b.     Out of the two blowers, one blower is used on a continuous basis and the other is a standby.  The water pumps are used 2 to 3 hours per day.  The process of shrimp production runs for about 40 to 50 days.

c.      The hatchery could not be run at the full capacity due to depressions, rains etc. from 09/2005 to 11/2005.  2/3rd of the hatchery is in outdoor while 1/3rd is indoor.  It is not possible to run outdoor hatchery at full capacity during rainy season.  Their consumption pattern for the previous 3 months was much less than the 13695 units shown in 09/05, as follows:

 

May, 2005

-

8820 units

June, 2005

-

4557 units

July, 2005

-

8475 units

August, 2005

-

3768 units

 

d.     The respondent No. 1 and 2 were informed that the shrimp production was stopped from 13-09-2005.

 

4.        As required under clause 8 (1) (c) and clause 11 of the Regulation No. 1 of 2004 of the Hon’ble APERC, the Ombudsman endeavoured to arrive at a mutually acceptable settlement and for this purpose a conciliation meeting was held at Tenali on 05-12-2006 in the office of Divisional Engineer / Operation, Tenali.  While there was no settlement, it was suggested to make efforts to retrieve the data from the meter through MRI so as to have the data of the record stored in the memory of the meter. 

 

 

5.        As no settlement was reached, by notice dated 20-12-2006 the respondents were directed to file counters by 12-01-2007 with copy to the appellant and the appellant was asked to file rejoinder, if any by 25-01-2007, with copy to the respondents, and the hearing was fixed on 05-02-2007 in the office of the Ombudsman at Hyderabad.  The Respondents No. 1, 2 and 4 have filed similar counters in their letters dated 06-01-2007.  The respondent No. 3 filed a separate counter (received on 19-01-2007) along with certain data concerned with this matter.  No rejoinder was filed by the appellant.

 

6.        In the counters, the respondents 1, 2 and 4 have merely enclosed copy of the report dated 08-01-2007 of the Assistant Divisional Engineer / LT Meters / Guntur wherein it was stated that it is the Omniagate meter of this service was tested on    14-11-2005 and found with “no-display”, and from such display failed meter, the MRI data cannot be taken as the CMRI shows unable to sign and final reading also not available.  They sought dismissal of the appeal on this ground.  The respondent No. 3 has furnished the data of monthly meter readings, units consumed, bills raised and payments made from May, 2004 onwards and stated that the consumer has not paid the amount of Rs. 53,662 claimed in 09/05 bill.  He requested for dismissal of the appeal.

 

7.        The parties herein were heard on 05-02-2007 in the office of Ombudsman (APERC office) at Hyderabad.  Sri.P. Chiranjeevi, Managing Partner of the appellant firm has re-iterated the contents of his appeal as well as the points deliberated in the conciliation meeting held on 05-12-2006 at Tenali.  The focus of his pleading is that the staff of the hatchery have seen the meter reading on 30-10-2006 and found the reading as 31,887 as against 40,609 noted in the bill of September 2005.  Hence the meter reading was wrongly mentioned and wrong bill was made.  He furnished a copy of the letter dated 30-10-2005 of M/s. Sridevi Hatchery addressed to Additional Assistant Engineer / Operation / Rural.  He explained that the hatchery works at maximum capacity during the period from February upto May and then they will reduce gradually section by section.  He further said that there was depression / cyclones in September 2005 and hence the hatchery did not work to its full capacity in September, 2005.

 

8.        The respondents represented by Assistant Divisional Engineer / Operation / Bapatla on the other hand have contended that the meter reading taken in September 2005 is correct and the consumer’s version is not correct.  They further stated that by 30-10-2006, the subsequent meter reading of October 2005 was also taken on 10-10-2005, which was noted as 41769.  Thus the consumer’s statement of meter reading on 30-10-2006 being 31, 887 is not correct.  They also stated that there was no severe cyclone or depression which could badly affect the hatchery work.

 

9.        In the above background of the rival contentions, the point for consideration in this appeal is whether the consumption billed in 09/05 bill is in order?

 

10.      To decide the point in para 9 above, it is necessary to examine whether the meter reading was wrongly noted or whether meter was defective or whether the meter was ok, at the time of the taking meter reading in September, 2005 (10-09-2005).  Further, whether there was any evidence for the meter reading of 31,887 mentioned by the appellant as on 30-10-2005?

 

           There is no evidence on record to prove that the meter was defective during September, 2005.  There is also no evidence to prove that the reading was wrongly noted by the respondents on 10-09-2005, except the letter dated 30-10-2005 of the appellant.  The appellant could not produce any other record like the register of meter readings if any, maintained by the consumer.  Further this reading was stated to be reported by the staff of the hatchery.  There is no supporting proof on correctness of such meter reading.  Thus it is difficult to rely on the meter reading mentioned by the consumer as on 30-10-2006.

 

           Now coming to the issue of defectiveness of the meter, it is pertinent to note that the meter eventually became defective by 1st November, 2005, as no display was found at the time of inspection by the respondents on 01-11-2005 after receipt of letter dated 30-10-2005.  The meter was replaced on 14-11-2005.  It is further to be noted that the make of this meter is Omniagate company whose meters are found to be defective in respect of single phase meters which were reported to have been withdrawn from service.  It is difficult to know the behaviour of the Electronic meters before they develop any defect as they are new and there is no past history.  Having regard to the fact that the meter of this service developed defect by 31st of October 2005 (as there was no display on 01-11-2005) it is reasonable to assume that the meter might have malfunctioned before it finally became defective.  Thus, either the reading of 31,887 reported to have been seen by the staff of the hatchery might be due to the malfunctioning of the meter and even the earlier readings of October / September, 2005 might also be due to malfunctioning.  It is therefore reasonable to assume that the meter might be malfunctioning during the disputed month of September, 2005, giving the benefit of doubt in favour of consumer which is just and fair in the circumstances of this case.

 

           Having decided that the meter might have malfunctioned from September, 2005, the assessment of energy consumption is to be done on the basis of average of previous 3 months consumption as follows:

 

June, 2005

-

4557 units

July, 2005

-

8475 units

August, 2005

-

3768 units

Total for 3 months

-

16800 units

Average per month

-

5600 units

 

           Thus, the consumer is liable to pay for a consumption of 5600 units instead of 13,965 units billed earlier for September, 2005.

          

           It is pertinent to note here that when once the meter is considered defective from September, 2005 onwards it follows that the reading for October, 2005 would also be defective and hence the bill for October, 2005 also requires to be revised.  However, if average consumption of last 3 months is applied, the bill requires upward revision, which would be against the spirit of consumer of consumer protection envisaged in the Electricity Acts, more so when the consumer (appellant) is pleading that the hatchery was stopped from 13-09-2005.  Considering this aspect and as seen from the consumption recorded after the meter was changed on 14-11-2005, it is considered that the bill of October, 2005 need not be revised.  During the hearing, both the parties have confirmed that the dispute is only in respect of September, 2005 bill.

 

11.      Award :

 

           Concluding the above discussion, I decide the following award in this appeal.

 

           The respondents shall revise the September, 2005 bill on the basis of consumption of 5600 units and the consumer shall pay the amount of such revised bill within 15 days from the date of receipt of the revised bill. 

 

12.      The Respondents are required to implement this award only after receipt of acceptance in writing for this award in toto from the appellant as required under clause 12 of the Regulation No 1 of 2004 of the Hon’ble APERC.  The revised bill shall be issued only after receipt of acceptance letter of the appellant for this award.

 

13.      Reasons for delay:   There is a delay of about a week over the period of 3 months specified by the Hon’ble Commission for disposal of the appeals in the Regulation No. 1 of 2004, which is mainly due to the schedule of work as Secretary in conducting Public hearings in January, 2007 in respect of ARR / Tariff filings of DISCOMs for 2007-08.   No one is responsible for the delay.

 

 

 

This Order is signed by me on the 20th of February 2007


 

 

VIDYUT OMBUDSMAN