VIDYUT
OMBUDSMAN
5th Floor, Singareni Bhavan, Red Hills,
Hyderabad –500 004.
Dated: 01-09-2006
Present: S. Surya Prakasa Rao
Ombudsman
M/s.
Mallikarjuna Rice Mill
Prop.
Pallerla Rajesh
S.C.No.691
/ Cat-III
Godavarikhani
and
1. Divisional
Engineer / Operation / Peddapally.
2. Assistant
Divisional Engineer / Operation / Godavarikhani
3. Assistant
Accounts Officer / ERO / Godavarikhani
This
appeal dated 22-06-2006 from Sri.P.Rajesham, (hereinafter called the appellant
or consumer) the proprietor of Mallikarjuna Rice Mill, Godavarikhani,
Karimnagar District against the order dated 18-05-2006 of the Forum for
redressal of grievances of consumers (hereinafter called the Forum or CGRF)
NPDCL, Warangal in C.G.No.52/2005 (Karimnagar Circle), coming up before the
Ombudsman and having stood over the matter till this day, the Ombudsman issues
the following:
O R D E R
2. The facts on record in this case are briefly narrated
here in. The appellant is availing power
supply to his rice mill at Godavarikhani, Karimnagar District for a connected
load of 74 HP from 31-10-2001, with S.C.No.GNR/691, under LT Ctegory III(A)
Industrial Normal Category. This
service was provided with metering on HT side of the DTR as per the conditions
specified on the tariff order (HT metering to be provided for loads of 50 HP
and above). In May 2003, the AAO/ERO
Godavarikhani (Respondent No.3) issued bill, which includes Low Power Factor
(LPF) surcharge amounting to Rs.43,178 for the months of December 2002 to March
2003. Subsequently also the LPF
surcharge was continued to be levied every month when ever the power factor
computed as the HT meter readings was below 0.9. Thus a total amount of Rs.60,150/- was levied as surcharge for the
period from December 2002 to February 2004 i.e. for a period of 15 months. The consumer protested for the levy of
surcharge and approached the local officers including DE/Operation/Peddapally
(Respondent No.1) and SE/Operation/Karimnagar.
As the issue was not resolved by the officials of Licensee, the consumer
approached the Forum of NPDCL, at Warangal on 06-02-2006 with a complaint on
LPF surcharge. The learned Forum
enquired into the complaint and reduced the surcharge from Rs.60,150 to
Rs.35,716 for the period from December 2002 to February 2004 vide its order
dated18-05-2006. Not satisfied with the
decision of the Forum, the consumer filed this appeal.
3. In his appeal dated 22-06-2006 the appellant made the
following prime contentions:
(i)
The surcharge of
Rs.43,178 for the period of December 2002 to February 2003 was levied only in
May 2003, along with the monthly bill of May 2003.
(ii)
The 25 KVAR rating
capacitors installed by him, are in working condition.
(iii)
He does not know why
surcharge is levied.
(iv)
Concerned officials
checked the capacitors after the consumer made representation and found that
the capacitors are working.
(v)
The rice mill became
sick due to lack of work on account of drought conditions.
(vi)
The CMD/NPDCL
considered the sickness of industry and waived minimum charges but LPF
surcharge was not waived.
(vii)
The Forum did not
clarify why surcharge is levied when capacitors are working and it did not
consider his grievance on that account.
For all the above reasons, the appellant
requested the Ombudsman to cancel the surcharge wrongly levied.
4. As required under clause 8(1)(C) of the Regulation
No.1 of 2004 of the Hon’ble Commission, the Ombudsman, by notice dated
24-06-2006, requested the parties herein to endeavour to arrive at a mutually
acceptable settlement by 14-07-2006. In
the said notice it was informed that if no settlement is reached, the
respondents are required to file the counter by 17-07-2006 and the appellant is
required to file his rejoinder if any by 24-07-2006, and that the Ombudsman will
hear the parties at Hyderabad on 31-07-2006.
5. As no settlement could be reached, the
AAO/ERO/Godavarikhani (Respondent No.3) filed his written statement in his
letter dated 11-07-2006. The other
respondents have not filed any written statements. The consumer (appellant) did not file any rejoinder to the
written statement of respondent No.3.
6. In his written statement dated 11-07-2006, the
respondent No.3 made the following prime submissions:
(i)
The Rice Mill was under
disconnection from March 2004 and bills were stopped from July 2004.
(ii)
On a representation of
the consumer on the ground of sick industry, the CMD/NPDCL issued certain
instructions in Memo dated 11-03-2006.
(iii)
As per the instructions
in the said Memo, out of the total dues of Rs.1,59,987, an amount of Rs.82,223
was withdrawn towards reliefs granted as sick industry and an amount of
Rs.67,298 was kept in abeyance pending decision of the Forum on consumer’s
complaint about LPF surcharge and the balance amount of Rs.10,366 was collected
from the consumer on 23-04-2006.
(iv)
Subsequently the Forum
decided the LPF surcharge as Rs.35,716 and hence the consumer has to pay only
Rs.35,716 (as against Rs.67,298 kept in abeyance).
(v)
The consumer came to the
ERO for settlement, but he is not agreeable to pay the amount, as per the order
of the Forum.
7. As it was felt desirable to conduct the hearing at
the place of the event so as to have better access to the records and also to
be more convenient to the appellant/respondents, the venue for the hearing was
changed to Godavarikhani and the same was informed to the parties by notice
dated 19-07-2006. The hearing was
conducted in the office of AAO/ERO/ Godavarikhani (Respondent No.3) on
31-07-2006. The Appellant as well as
all the 3 respondents have attended the hearing.
8. During the hearing on 31-07-2006 the appellant
Sri.P.Rajesham made the following oral submissions:
(a)
He has not received any
notice from the respondents about defect in the capacitors installed by
him. The capacitors installed by him
are working and no defect was noticed.
(b)
As instructed by the
respondent No.2, additional 10 KVAR capacitors were installed and connected in
addition to the 25 KVAR capacitors already installed. Again another 10 KVAR capacitors were brought recently and kept
in the premises as instructed by the respondents.
(c)
The respondents are
demanding payment of arrears without giving full account of the payments made
by him.
When I asked him to inform how he is able
to assert that the capacitors were working and there is no defect, he could not
give any definite answer. He believes
that they are O.K. as no defect was pointed out by the respondents.
9. Sri.U.V.Chari AAO/ERO/Godavarikhani (Respondent No.3)
provided the following information at the time of hearing on 31-07-2006.
·
Date of release of
supply 31-10-2001
·
HT metering is provided
at the time of release of supply as seen from the Test report at the time of
release of supply to this service.
·
Power factor data
available from June 2002.
·
Respondent No.3 issued
notice on 31-03-2003 to pay Rs.40,891 towards LPF for the period from December
2002 to March 2003.
The AAO furnished a copy of the Test
report dated 11-10-2001 on testing of HT meter installed for this LT service. The said report contains a remark that
required number of capacitors may be connected before release of supply to the
consumer load. The meter was tested on
phantom load as the consumer was not ready with his load. This shows that the capacitors were not
installed by the date of testing of meter on 11-10-2001. However as the supply was released on
31-10-2001, it could be presumed that the required capacitors would have been
installed by that time as the LT supply would not have been released without
capacitors as per clause 38.9 (b) of the Terms and conditions of supply (here
in after called as TCS).
10. Sri.T.Venumadhav, ADE/Operation/Godavrikhani
(Respondent No.2) has stated that the low power factor values computed as per
the reading of HT metering were informed to the consumer at the time of taking
the monthly meter readings. In response
to my question whether any Test report is available in the records on testing
of meter any time subsequent to the release of supply, the ADE has stated that
the meter was again tested on
18-11-2002 by MRT and the same will be furnished separately. He also stated that notice on defect of
capacitors was issued on 31-01-2006 as per inspection on 22-01-2006. When I requested for the record of test
results, he said that the record was not kept.
He expressed the opinion that the consumer is liable to pay LPF
surcharge since the power factor is less than the specified level of 0.9.
11. In the background of the rival contentions and facts on
record as detailed above, the point for consideration is
“Whether the LT III(A) – Industrial
normal category consumer is liable to pay surcharge even after installing the
capacitors of required ratings as per
TCS and when no defect was established in the capacitors?
and
Whether the respondents are entitled to
levy the LPF surcharge on LT III(A)
Industrial normal category consumers on the basis of the power factor computed
from the readings recorded in the HT metering provided for such consumers?”
12. POINT:
This matter is squarely covered by the
matters earlier decided by the Ombudsman in Appeal No.7 of 2006 (M/s. Pranav
Rice Mill, Adilabad District) and Appeal No. 9 of 2006 (M/s.Saraswathi Binni
Rice Mill, Khammam District). The
provisions of TCS/Tariff orders on the basis of which, the decisions in these
cases are taken are indicated in the Annexure to this order. They are briefly mentioned here under:
(i)
Part ‘D’ of the Tariff
orders of 2002-03 and 2003-04 (which are relevant for the period for which the
surcharge was levied) provides that if the capacitors already installed by LT
consumers are found to be defective during inspection, such consumers shall
attract penal provisions as per the TCS.
(ii)
The levy of surcharge
incase of LT consumers is governed by clause 38.9(a) of the TCS which requires
issue of notice informing that the capacitors are defective and asking the
consumer to rectify/replace such defective capacitors, with in one month.
(iii)
LPF surcharge as per HT
metering is leviable only on LT III(A) Industrial optional category consumers
and not LT III(A) Industrial normal category consumers as per condition
V(c) of Note under LT category III(A), in part B, of Annexure D of Tariff order
of 2003-04, and as per condition VI under LT Category III(B)
In this case it is established beyond any
doubt that no inspection was done to establish the defect in capacitors and no
notice was issued on that basis before levy of surcharge during the period from
December 2002 to February 2004. The
notice dated 31-03-2003 issued by the respondent No.3 does not however mention
about the defect in the capacitor nor an opportunity was given for
rectification as required under the TCS.
Regarding the authority to levy LPF surcharge on the basis of the power
factor computed from the readings of HT metering, it is to be stated that the
item (iii) above makes it clear that the LPF surcharge (as in the case of HT
consumers) is leviable only for LT III(A) Industrial optional category consumers
and not for LT III(A) Industrial normal category consumers. Hence the respondents have no authority to
levy the LPF surcharge on LT III(A) Industrial normal category consumers during
the period under consideration. Thus
the point is proved in favour of consumer.
13. Before pronouncing the award it would be of some use
if the rationale/logic in not reckoning the power factor obtained in HT
metering for the purpose of levy of surcharge in these cases, is explained
apart from the rule position stated above.
In the case LT supply to any consumer, the DTR is the equipment of
Licensee though it is exclusively installed for certain consumers including
those for whom meter is provided on HT side of DTR. The reactive load of the DTR will influence the average power
factor and its impact would be substantial in the case of Industries, which run
only for a few hours in a day in the month.
In fact it was established from the meter test reports in the Khammam
case referred above, that the instantaneous power factor when the consumer was
running the load was very near to 0.9, as against the average power factor
computed for an entire month being around 0.5 or so. Thus the impact of licensee’s DTR is substantial in the cases
where the Industry works only for few hours in a day. In this case no record is made available to establish the
instantaneous power factor obtained during running of the consumer load
vis-à-vis the monthly average power factor.
The MRT test report dated 18-11-2002 promised to be furnished by the
respondent No.2 has not yet been furnished.
However for the period under consideration i.e. during 2002-03 and
2003-04 the TCS as well as Tariff conditions do not provide for levy of
surcharge merely on the basis of HT meter readings in so far as LT III(A)
normal category consumers are concerned.
14. It is also necessary to make an observation that the
Licensee’s officials (respondent No.1 and 2) could have examined the problem in
detail and would have suggested to connect capacitor of suitable rating
directly before the main switch so that these capacitors will be in service
irrespective of usage of load by the consumer, as rightly suggested by the
DE/Operation/Adilabad in the Pranav Rice Mill case (in Appeal No.7 of 2006)
referred above. Even now it is
desirable that the respondents may suggest suitable modifications in the
arrangement of capacitors of appropriate rating before main switch.
15. Concluding the above discussion, I decide the
following award in this appeal:
(i)
The LPF surcharge
levied during the period form December 2002 upto February 2004 shall be
withdrawn, as it is not leviable.
(ii)
The respondent No.3
shall serve a supplemental bill for the balance amount payable after revising
the bills for the period as indicated in (i) above.
(iii)
The consumer shall pay
the balance amount due if any with in 15 days from the date of issue of such
supplemental bill failing which the respondents shall be at liberty to take
appropriate action as per the TCS.
15. The respondents are required to implement this award
only after the appellant gives his consent for this award in terms of clause 12
of the Regulation No.1of 2004.
This order is signed on the
1st day of September 2006.
VIDYUT OMBUDSMAN
To
1. P. Rajesham at the following address as
requested by appellant.
H.No.1-1-287/20/1
Bapunagar, Municipal Market Street
Chikkadpalli
Hyderabad – 500 020
2. Divisional Engineer / Operation /
Peddapally.
3. Assistant Divisional Engineer / Operation /
Godavarikhani
4. Assistant Accounts Officer / ERO /
Godavarikhani
Copy
to
The
Chairperson,
Forum
for redressal of grievances of consumers,
NPDCL,
Warangal.
The
Secretary,
APERC, Hyderabad.
Annexure
The relevant provisions of
TCS and the tariff conditions of Tariff order of the relevant period
Clause 38.9(a): “Power Factor of apparatus other than welding
Transformer: Every L.T. consumer using induction motors shall instal L.T. shunt
capacitors of specified rating as given below.
|
SI.No. |
Rating of individual motor |
KVAR rating of L.T. Capacitors
for various R.P.M. of the
motors |
|||
|
750 RPM |
1,000 RPM |
1,500 RPM |
3,000 RPM |
||
|
1. |
3 h.p. |
1 |
1 |
1 |
1 |
|
2. |
5 h.p. |
2 |
2 |
2 |
2 |
|
3. |
7.5 h.p. |
3 |
3 |
3 |
3 |
|
4. |
10 h.p. |
4 |
4 |
4 |
3 |
|
5. |
15 h.p. |
6 |
5 |
5 |
4 |
|
6. |
20 |
8 |
7 |
6 |
5 |
|
7. |
25 h.p. |
9 |
8 |
7 |
6 |
|
8. |
30 h.p. |
10 |
9 |
8 |
7 |
|
9. |
40 h.p. |
13 |
11 |
10 |
9 |
|
10. |
50 h.p. |
15 |
15 |
12 |
10 |
If
the existing consumer fails to install capacitors of required rating within
such time as may be fixed by the Board, such of those consumers as may be
specified by the Board are liable to pay surcharges as may be fixed by the
Board from time to time. If the
capacitors already installed are found, during inspection, to be damaged or
become defective or cease to function, the consumer shall be served with a
notice to get the same replaced/rectified or corrected within 30 days of the
inspection and intimate the fact of replacement/rectification to the concerned
Section Officer, Operation, of the Board, who will inspect the capacitors again
to verify their satisfactory performance.
In the event of failure on the part of the consumer to comply with the
above notice, the Board may levy a surcharge of 25% per month on the bill
amount or as may be prescribed by the Board from time to time from the date
from which the capacitor was defective or ceased to function till such time the
capacitor is replaced/rectified or corrected., Provided further that such
retrospective levy of surcharge shall be limited to one year from the date of
inspection. The consumer aggrieved by
the retrospective levy, may appeal to the concerned Superintending Engineer,
Assessments, whose decision shall be final.
The failure on the part of the consumer to comply with the above notice,
shall be treated as violation of Terms and Conditions of Supply and Board
reserves the right to terminate the contract and collect the balance initial
period agreement.”
Clause 38.10(a): “Every consumer whose connected load includes welding
transformer shall install L.T. shunt capacitors of the capacity mentioned in
clause 38.10.1 and 38.10.2 for improving the power factor. If the existing consumers fail to install
capacitors of required rating within such time as may be fixed by the Board
such of these consumers as may be specified by Board, are liable to pay
surcharge, as may be fixed by the Board from time to time.
If
the capacitors already installed are found, during inspection to be damaged or
become defective or cease to function, the consumer shall be served with a
notice to get the same replaced/rectified or corrected within 30 days of the
inspection and intimate the fact of replacement/rectification to the concerned
Section Officer (Operation) of the Board, who will inspect the capacitors again
to verify their satisfactory performance.
In
the event of failure on the part of the consumer to comply with the above
notice, the Board may levy a surcharge of 25% per month on the bill amount or
as may be prescribed by the Board from time to time from the date from which
the capacitor was defective or ceased to function till such time the capacitor
is replaced/rectified or corrected.
Provided further that such retrospective levy surcharge shall be limited
to one year from the date of inspection.
The consumer aggrieved by the retrospective levy, may appeal to the
concerned Superintending Engineer/ Assessments, whose decision shall be final.
The
failure on the part of the consumer to comply with the above notice, shall be
treated as violation of Terms and Conditions of Supply and Board reserves the
right to terminate the contract and collect the sum equivalent to the minimum
charges for the balance initial period of agreement.”
Clause 23 of TCS
“23:
Surcharges for lower power Factor: The power factor for the month
shall be the ration of Kw hours to the Kilo-Volt Ampere-Hours supplied to the
consumer during the month. The power
factor shall be calculated upto two decimal places. The power factor of the consumer’s installation shall not be less
than 0.90. If the power factor falls
below 0.90 during any month, the consumer shall pay a surcharge as detailed
below.
|
SI.No. |
Power factor Range |
Surcharge |
|
1. |
Below 0.90 & upto 0.85 |
1% of c.c. charges bill of
that month for every fall of 0.01 of power factor from 0.9 |
|
2. |
Below 0.85 & upto 0.80 |
1.5% - do - from 0.85 |
|
3. |
Below 0.80 & upto 0.75 |
2% - do - from 0.80 |
|
4. |
Below 0.75 |
3% - do - from 0.75 |
Should
the power factor drop below 0.75 and so remain for a period of 2 consecutive
moths, it must be brought to 0.90 within a period of 6 months by methods
approved by the Board failing which without prejudice to the right of the Board
to collect the surcharge and without prejudice to such other rights as have
accrued to the Board or any other right of the Board, the supply to the
consumer may be discontinued.”
Relevant
Provisions of Tariff Orders
“Note:
Conditions under LT Category III(B), Part B, LT Tariffs of Tariff order (2002-03)
(i)
. . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(vi)
The Low Power Factor (LPF) surcharge is applicable as
in the case of HT consumers for LT Category III(A), optional & III(B)
Note: under LT
category III(A), part B, LT Tariffs of Tariff order (2003-04)
(ii)
. . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(v)
(a) . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . .
(b) For
loads 50HP to 75HP the metering will be provided on HT side of the Distribution
Transformer.
(c)
The Low Power Factor (LPF) surcharge is applicable as
in the case of HT consumers for LT Category III (A) Industrial – Optional
demand tariff category.”
“(6) SURCHARGE FOR LOW POWER
FACTOR
The power factor for the month shall be the ratio of
Kilo-Watt hours to the Kilo-Volt-Ampere Hours supplied to the consumer during
the month. The power factor shall be
calculated upto two decimal places. The
power factor of the consumer’s installation shall not be less than 0.90. If the power factor falls below 0.90 during
any month, the consumer shall pay a surcharge as detailed below:
|
S.No. |
Power
Factor Range |
Surcharge |
|
1. |
Below 0.90 & upto 0.85 |
1% of C.C. charges bill of that
month for every 0.01 fall in Power Factor from 0.90 |
|
2. |
Below 0.85 & upto 0.80 |
1.5% of C.C. charges bill of
that month for every 0.01 fall in Power Factor from 0.85 |
|
3. |
Below 0.80 & upto 0.75 |
2% of C.C. charges bill of that
month for every 0.01 fall in Power Factor form 0.80 |
|
4. |
Below 0.75 |
3% of C.C. charges bill of that
month for every 0.01 fall in Power Factor from 0.75 |
Should the
power factor drop below 0.75 and so remain for a period of 2 consecutive moths
it must be brought upto 0.90 within a period of 6 months by methods approved by
the Licensee failing which, without prejudice to the right of the Licensee to
collect surcharge and without prejudice to such other rights as having accrued
to the Licensee or any other right of the Licensee, the supply to the consumer
may be discontinued.”
Part ‘D’ of Annexure D of the Tariff Order (2002-03).
1. FOR H.T. AGRICULTURAL CONSUMERS
Every
H.T. Agricultural Consumer using induction motors shall install L.T. Shunt
capacitors of specified rating as given below:
Table of rating of capacitors
|
2. FOR L.T. CONSUMERS
Every
L.T. Consumer using induction motors and welding transformers shall install
L.T. Shunt Capacitors of specified rating as given below:
(a) Motors
|
Table of rating of
capacitors |
(b) Welding transformers
|
Table of rating of
capacitors |
NOTE
1.
If
any such consumer fails to install the capacitors at all or fails to install
the capacitors of required rating or the capacitors already installed are found
during inspection to be damaged or become defective or ceased to function, the
consumer shall attract penal provisions as per conditions of supply.
2.
Low
Power factor surcharge is not applicable for the consumers under the flat rate
tariff. Instead, these consumers are
required to install L.T.Shunt Capacitors of specified rating as indicated in
these Tariffs annexed, failing which they are liable to pay capacitor surcharge
at the rates indicated in Part-‘D’. In
case the L.T.Shunt Capacitors of specified rating are not installed within one
month period from date of notice after detection, without prejudice to right of
the Licensee to collect surcharge and without prejudice to such other rights
having accrued to the Licensee or any other right of the Licensee, the supply
to the consumer may be discontinued.
The consumer attracts the penal provision as per the conditions of
supply.
3.
In
case the rated capacity of the welding transformer falls in between the steps
of the stipulated ratings, the capacitors suitable for the next higher step
shall be installed by the consumer.
4.
The
failure on the part of the consumer to comply with the above requirement shall
be treated as violation of terms and conditions of the supply and the Licensee
can terminate the contract and collect the sum equivalent to the minimum
charges for the balance initial period of agreement.”
Part ‘D’ of Annexure D of the Tariff Order (2003-04).
1. FOR H.T. AGRICULTURAL CONSUMERS
Every
H.T. Agricultural Consumer using induction motors shall install L.T. Shunt
capacitors of specified rating as given below: