VIDYUT OMBUDSMAN
5th Floor, Singareni Bhavan, Red Hills,
Hyderabad –500 004.
Dated: 09-09-2006
Present: S. Surya Prakasa Rao, Ombudsman
Sri A.Satyanarayana
M/s.Sambasiva Rice Mill
S.C.No.1128
Piduguralla
Guntur (Dist)
… Appellant
and
1. Assistant Divisional
Engineer/Operation/Piduguralla
2. Junior Accounts
Officer/S-ERO/Piduguralla
3. Divisional
Engineer/Operation/Macherla
4. Superintending
Engineer/Operation/Guntur
5. Assistant Divisional
Engineer/LT.Meters/Guntur
…
Respondents
This appeal dated
21-06-2006 from Sri A.Satyanarayana, of M/s. Sambasiva Rice Mill, Piduguralla
(hereinafter called the consumer or appellant) against the order dated
01-06-2006 of the Forum for redressal of grievances of consumers (hereinafter
called the Forum or CGRF), Southern Power Distribution Company Ltd. (SPDCL),
Tirupathi in C.G.No.9/2006-07 (Guntur Circle) and having stood over till this
day, the Ombudsman issued the following:
2. The facts on record in this case are narrated briefly
herein M/s. Sambasiva Rice Mill has been availing supply from 1st
October 1996 for a contracted load of 45 HP with S.C.No.1128, Piduguralla,
Guntur District, under LT Category III.
The meter of this service was changed on 21-09-2000 pursuant to the
programme undertaken by TRANSCO/DISCOMs to replace the Electro-mechanical
meters of Industrial connections with Electronic tri-vector meters under APL –
1 scheme. On 04-05-2002, the new meter was
tested by ADE/LT Meters, MRT Guntur (respondent No.5) and found that the meter
was recording 33.3% less as the voltage in one (R phase) out of the 3 phases is recording zero. He found that ‘R’ phase potential is
connected over tape. He also examined
the MRI data and found that “missing potential” status started occurring from
31-10-2000 and hence recommended for back billing of Rs.1, 31,178 towards the
short recording of 31138 units for the period from 31-10-2000 to 04-05-2002, in
his letter dated 06-05-2002 addressed to the ADE/Operation/Piduguralla
respondent No.1, who issued notice on 31-08-2002 to the consumer about “missing
potential” and proposed back billing for the period from 31-10-2000 to
04-05-2002 for an amount of Rs.1,31,178.
The consumer made a representation to the DE/Operation/Macherla
(respondent No.3) on 25-09-2002 protesting the proposed back billing. The DE/Operation/Macherla in his proceedings
dated 19-07-2004 confirmed the back billing amount of Rs.1,31,178 and the same
was included in the monthly CC bill of June 2005. The consumer again protested for the back billing and made a
representation to SE/Operation/Guntur (respondent No.4) on 18-07-2005. There was no response on the said
representation. The consumer therefore
approached the CGRF, SPDCL Tirupathi, with a complaint on 04-05-2006. The learned Forum in its order dated
01-06-2006, while confirming the back billed amount of Rs.1,31,178, granted
some relief to the consumer by waiving the surcharge for belated payment till
15 days from date of its order. Not
satisfied with the decision of the learned Forum, the consumer filed this
appeal.
3. In his appeal the consumer raised the following prime
contentions:
(i)
He was not given
opportunity to examine the MRI data.
(ii)
As the power supply was
disconnected during the pendency of his complaint before the Forum, the supply
should be restored immediately and compensation should be paid for such
disconnection.
(iii)
Much delay was made to
issue orders on the various representations made to concerned officers, as per
the Terms and conditions of supply (TCS).
(iv)
The consumption pattern
during the year prior to inspection date (04-05-2002) and after that date
supports his contention that the MRI data and the instrument on which the (-)
error was arrived is wrong.
For all the above reasons, the appellant
sought withdrawal of the total back billed amount.
“The critical issue
to be decided is whether the 6 months limitation under section 26 (6) of the IE
Act 1910 is applicable even if the respondent him self proceeded to determine
the defective connections and assess the energy lost as per the Terms and
Conditions of Supply. The respondent
has vehemently contended that wrong connection to a meter is different from
defective meter and hence the limitation under Section 26 (6) of the Act is not
applicable in such cases. There is a
distinct difference between these two positions i.e. defective meter vs wrong
connection, from the viewpoint of ascertaining the probable date of development
of defect and level of error over the period of continuance of defective
status. In the meters, the defects may
arise on account of mechanical parts like the bearings that support the Disc
which rotates due to electromagnetic force of the Electrical windings or the
electrical windings getting damaged due to heat or over load / local conditions
/ surges etc., in electrical systems, over a period of time. Thus, it is difficult to exactly identify
the time of commencement of defect in a meter and also how the defect develops,
resulting in different levels of errors in measuring the energy over a period
of time. This could be the reason for
stipulating the statutory limitation on the period of back billing in respect
of defective meters. Whether such
limitation is applicable to cases of short measurement by a healthy meter due
to wrong connection is a moot question. The Legislature would not have foreseen
that Licensees would give wrong connections to the meter and hence such
contingency might not have been dealt in the Act.
This order is signed on the 9th day of
September, 2006.
VIDYUT OMBUDSMAN
To
1. Sri A.Satyanarayana
M/s.Sambasiva Rice Mill
S.C.No.1128
Piduguralla
Guntur (Dist)
2. Assistant Divisional
Engineer/Operation/Piduguralla
3. Junior accounts
Officer/S.ERO/Piduguralla
4. Divisional
Engineer/Operation/Macherla
5. Superintending
Engineer/Operation/Guntur
6. Assistant Divisional
Engineer/LT.Meters/Guntur
Copy
to
The
Chairperson,
Forum
for redressal of grievances of consumers,
SPDCL,
Tirupati.
The
Secretary, APERC,
Hyderabad.