V I D Y U T    O M B U D S M A N

O/o: The Secretary, Andhra Pradesh Electricity Regulatory Commission

 4th & 5th Floors, Singereni Bhavan, Red Hills, Hyderabad

 

Representation of M/s.Singareni Steel Private Limited stay of the order dated  06-10-2006 of CGRF/NPDCL in C.G.No.95/2006 of Khammam District –  Reg.

 

 

Proceedings No. VO/I.NO.31/06-12                                                                                                                                Dated 22-11-2006

 

 

Present: S. Surya Prakasa Rao,

          Vidyut Ombudsman

 

 

***

 

 

Whereas M/s.Singareni Steel Pvt. Ltd., Kothagudem, herein after called as the appellant or consumer, filed a representation (appeal) dated 18-11-2006 against the order dated 06-10-2006 of the Forum for redressal of grievances of consumers (herein after called CGRF or Forum) NPDCL, Warangal in C.G.No.95/2006 (Khammam Circle), and

 

2.         Whereas the consumer also filed a representation dated 18-11-2006 seeking stay of collection of disputed demand till the appeal is disposed off by the Ombudsman, and

 

3.         Whereas the Ombudsman, having regard to the circumstances of this case, considers it just and reasonable to stay the action pursuant to the order of the learned Forum, and

 

4.         Accordingly, the Ombudsman directs the Respondents in C.G.No.69/2006 (Khammam Circle) of the CGRF Warangal not to take any co-ercive action to collect the demand raised pursuant to the said order dated 06-10-2006 of the learned Forum of NPDCL, Warangal, upto 05-01-2006 i.e. for a period of 3 months from the date of the order of the learned Forum.

 

5.         Notice to parties issued separately on the said appeal.          

 

VIDYUT OMBUDSMAN