ANDHRA PRADESH
ELECTRICITY REGULATORY COMMISSION
Hyderabad
Dated: 09-07-2007
Present
Sri K. Swaminathan,
Chairman
Sri Surinder Pal, Member
Sri. R. Radha Kishen, Member
O. P. No. 40 of 2006
and
I.A.No.2 of 2007
Between
M/s. Hyderabad
Chemical Products Limited,
# A-24/25,
APIE, Balanagar, Hyderabad - 037. …
Petitioner/petitioner
and
M/s. A.P.
Central Power Distribution Co. LTD.,
3rd
Floor, Singareni Bhavan, Red Hills, Hyderabad ...
Respondent
AND
O. P. No. 41 of 2006
and
I.A.No.3 of 2007
Between
M/s. Hyderabad
Chemical Limited,
Bank
Street, Hyderabad - 095. ...
Petitioner/Petitioner
and
M/s. A.P.
Central Power Distribution Co. LTD.,
3rd Floor, Singareni Bhavan, Red Hills, Hyderabad ... Respondent
These petitions
and IAs coming on for hearing on 23.06.2007 in the presence of Sri C. Kodanda
Ram, Advocate, for the petitioners in both the cases and Sri P. Shiva Rao,
Advocate, for the respondent in both the cases and having stood over for
consideration to this day, the Commission delivered the following common:
O R
D E R
Petitioners in the both
these petitions set up wind-based power projects of different capacities at
Kadavakallu Village, Anantapur district. The facts relating to establishment of
these projects after obtaining sanctions, permissions and approvals from
authorities concerned are not in dispute and therefore, it is not necessary to
delve into those details.
2. The petitions and the IAs are filed under Section 86(1)(f)
of the Electricity Act, 2003 (hereinafter, ‘the Act’) and are based on the same
set of facts, with identical prayer. Therefore, they are clubbed together and
decided by this common order. The common prayer in the two petitions is to
direct the respondent, a distribution company / licensee (hereinafter also
referred to as ‘APCPDCL’) to pay the petitioners for the power generated and
pumped into the grid from their generating stations with effect from 31.03.2005
and to pass such other order or orders as deemed fit and proper by this
Commission in the interest of justice.
3. Earlier the petitioners herein had
filed separate petitions in O.P.Nos.9 and 10 of 2006 respectively containing
identical averments for directions to the respondent herein (i) to purchase
electricity from the petitioners, and (ii) to pay the petitioners for the power
pumped into the grid from the petitioners’ generating stations with effect from
31.03.2005.
4. As the relief claimed by the
petitioners herein is the same as in the earlier petitions referred to above,
the present petitions were admitted subject to maintainability on res-judicata and notices were issued to
the respondent.
5. The Interlocutory Applications (I.A.Nos.2 & 3 of 2007 in
O.P.Nos.40 & 41 of 2006 respectively) are filed on behalf of the
petitioners herein stating that due to inadvertence, interest on the amounts
due to the petitioners for the power generated and pumped into the grid from
their generating stations was not claimed. Therefore, it is requested to permit
the petitioners to amend the prayer in the main petitions and accordingly direct
the respondent to pay the petitioners herein for the power generated and pumped
into grid from their generating stations with effect from 31.03.2005 till
08.06.2006 along with interest at 16% per annum and pass such other order or
orders as deems fit and proper in the interest of justice. The petitioners also
requested that the IAs may be heard along with the main petitions.
6. Separate counters were filed on behalf
of the respondent in I.A Nos.2 & 3 of 2007 with the similar objections on
procedural as well as on merits of the case. On behalf of the respondent, it is
stated that the applications ought to have been filed under clause 55 of the
Commission’s Conduct of Business Regulations. The amendment sought is
distinctly different from the claim made in the main petitions. The claim made
by the petitioners in O.P.Nos.40 & 41 of 2006 is barred by the doctrine of res-judicata and therefore, interest on
the said claim is also barred by law.
For the said reasons, it is requested that the IAs may be dismissed.
7. Leaving aside the facts relating to establishment of the
wind-based power projects by the petitioners and other details which are not in
dispute as stated above, the following are the similar averments made by the
respective petitioners in the (main) petitions:
(i) The projects of the petitioners were synchronized with the
grid and commissioned on 31.03.2005. Even though both the petitioners were
pumping power into the grid, the respondent did not come forward to enter into
Power Purchase Agreements (for short, ‘PPAs’). On the other hand, the
petitioners were advised to avail Open Access facility and sell the power
generated to third parties stating that the respondent is not interested in
purchasing electricity produced by the petitioners. Having no other
alternative, the petitioners filed petitions in O.P.Nos.9 & 10 of 2006 as
stated above, requesting the Commission to direct to the respondent to purchase
electricity generated by the petitioners and to pay for the power pumped into
the grid from the generating stations of the petitioners from 31.03.2005.
(ii) By a common order dated 01.04.2006 in O.P.Nos.9 & 10 of
2006, the Commission dismissed the said petitions. Subsequent to passing of the
said order, the petitioners approached the respondent for entering into the
PPAs and accordingly, the petitioners entered into separate PPAs with the
respondent on 09.06.2006. Vide proceedings dated 24.06.2006, the Commission
granted consent to the said PPAs as required under section 21(4)(b) of the A.P.Electricity
Reform Act, 1998.
(iii) On 24.06.2006 itself, the petitioners wrote letters bringing
to the notice of the respondent that the projects of the petitioners were
synchronized with the grid in the month of March, 2005, joint tests of the meters
installed at the inter-connection points at project switchyards were conducted,
and joint meter test reports were obtained from the office of the Chief
Electrical Inspector General, Government of Andhra Pradesh, and accordingly
requested the respondent to pay for the electricity generated and pumped into
the grid.
(iv) Subsequently, the petitioners wrote letters on 29.08.2006
requesting the respondent to expedite payments as the petitioners were in
financial trouble. As per the advice of the respondent, the petitioner in
O.P.No.41 of 2006 raised an invoice on behalf of itself as well as on behalf of
the petitioner in O.P. No. 40 of 2006 for a total amount of Rs.2,94,07,860 for
the energy delivered by them during the period 31.03.2005 to 21.08.2006. However,
the Chief General Manager (Comml & RAC) of the respondent informed the
petitioners vide letters dated 28.08.2006 and 29.08.2006 that the respondent
would pay for the power received by it for the period after 09.06.2006, the day
on which the PPAs were entered into. It was further informed that the bills of
the petitioners were being processed accordingly, as per the agreed tariff and
that no payment will be made in respect of the electricity pumped into the grid
prior to entering into PPAs. Rejection of the claim of the petitioners for
payment for the power drawn by the respondent during the period 31.03.2005 to
08.06.2006 is arbitrary, illegal and contrary to the terms of the PPAs dated
09.06.2006.
(v) A plain reading of Articles 1.3,
1.4,1.8, 2.1, 2.2 and 4.10 of the PPAs would go to show that the electrical
energy generated by the projects and delivered to the respondent at the
interconnection point i.e., the point of metering will be purchased at the rate
of Rs.2.70 per unit from and after the date of commercial operation (for short,
‘COD’) of the project. COD of the projects in the present cases is the date of
synchronization of the 1st unit of the projects i.e., 31.03.2005 as
is evidenced by the letter dated 15.04.2005 and meter readings furnished by the
Divisional Engineer, Wind Farms Division, Anantapur.
(vii) It is admitted case of the respondent that the power generated
by the projects of the petitioners was pumped into the grid since 31.03.2005
and the power so exported has been recorded every month. Hence there is no
dispute with regard to the quantum of the power pumped into the grid.
(vii) The petitioners have incurred substantial sums of monies in
setting up their wind energy projects after borrowing the same from the banks
and financial institutions and have made infrastructure additions in one of the
most underdeveloped parts of the State. The petitioners are obligated to
service the loan amounts and as such they have been paying the interest by
making further borrowings as the projects are not generating any cash flows.
8. The respondent filed separate counter affidavits in both the
petitions. The identical replies submitted by the respondent are as under:
(i). The relief claimed in these two cases was subject matter of O.P.Nos.9
and 10 of 2006, vide Issue No.(ii) framed by the Commission in its order dated
01.04.2006 and after considering the pleadings of the parties concerned, the
Commission held that the respondent is not liable to pay for the energy
delivered by the petitioners from 31.03.2005 to the grid of the respondent. The
order of the Commission dated 01.04.2006 had attained finality as the
petitioners did not challenge it. Therefore, the petitioners are precluded from
reagitating on the same issue once again. As such the petitions are barred by
doctrine of res-judicata and are
liable to be dismissed in limine.
(ii). Even though the petitioners entered into PPAs with the
respondent after dismissal of O.P.Nos.9 and 10 of 2006, it would not give rise
to any fresh cause of action to the petitioners, more particularly in view of
their categorical commitment through letters dated 26.02.2005 and 31.03.2005 to
the effect that till the PPAs come into being whatever energy that is pumped
into the grid is free of cost, and held as such by the Commission as stated
above. Basing on such commitments, and their confirmation, the respondent
entered into PPAs with the petitioners. The petitioners are estopped from
saying otherwise than what they already said and claim for the cost of power
supplied to the grid prior to entering into PPAs.
(iii). When the petitioners proposed to sell energy to the respondent,
they were informed that they may opt for third party sales as is permitted
under the Act. Yet the petitioners decided to sell energy generated by their
projects to the respondent only which is obviously for their advantage. Without
prejudice to the stand of the respondent not to purchase power from the
petitioners, the petitioners were given evacuation arrangement which is necessary
for commencement of the projects and also interconnection facility from the
substation of the respondent. Thus, the respondent did not agree for banking of
energy also. Extension of evacuation and interconnection facilities to the
petitioners does not entitle them to claim for the energy pumped into the grid
of the respondent as the petitioners had agreed to do so free of cost in
writing, as stated above.
(iv) Believing that the written commitments of the petitioners as
contained in their letters dated 26.02.2005 and 31.03.2005 and the oral
commitments made just prior to entering into agreements are bonafide, the
parties entered into PPAs on 09.06.2006 with stipulations for future period.
Nowhere is it agreed between the parties that PPAs have retrospective effect or
that the energy pumped into the grid will be considered for billing. After
grant of consent by the Commission to the PPAs entered into between the parties
on 09.06.2006, through letters dated 24.06.2006 the petitioners requested the
respondent to process the payment for the energy of future generation, but not
for the energy generated that is already pumped into the grid.
(v) Even the letter dated 29.08.2006 does not speak of anything
about the energy already pumped by then and in fact, it is said that payment
may be made for the energy being pumped. It is false to say that officers of
the respondent company advised the petitioners to raise invoice for the energy
already delivered. The petitioners are put to strict proof of the same. On 09.09.2006,
the petitioners raised invoice for the energy pumped from 31.03.2005 to
21.08.2006, but the respondent categorically conveyed that it is not liable to
pay for the energy pumped prior to the PPAs i.e., 09.06.2006 and passed the
bill for payment for the energy pumped into the grid from 09.06.2006. The claim
of the petitioners is contrary to their written commitments and amounts to
criminal breach of trust.
(vi) It is not correct to state that the various clauses in the
PPAs show that the petitioners are entitled for payment for energy pumped with
effect from COD of the projects. The clauses need to be read along with the two
letters dated 26.02.2005 and 31.03.2005 and the order of the Commission dated
01.04.2006. The COD of the PPAs is unconnected to the energy already pumped
free of cost to the respondent.
(vii) Article 2.1 of the PPAs states that “All the delivered energy at the interconnection point for sale to
APCPDCL will be purchased at the tariff provided…..”. In this case, the energy delivered for sale is from 09.06.2006,
but not earlier to 09.06.2006. Similarly, Article 2.2 states that “…. the company shall be paid the tariff for
the energy delivered at the interconnection point for sale to APCPDCL ……”.
The said two clauses clearly exclude liability to pay for the energy that was
agreed to be pumped in free of cost. The words “for sale to respondent” should
not be divorced while interpreting the words “the payment of tariff of the
energy from the COD”.
(viii) The respondent is a public undertaking and the consumers are
the ultimately affected persons. In view of the public interest involved, the
principles governing the contracts between individuals are not applicable in
these matters and the petitioners are not entitled for any interest.
(ix)
For all these reasons, it is prayed that the petitions
may be dismissed.
9. On behalf of the petitioners, identical rejoinders were
filed stating that :
(i) It is incorrect to state that the issue raised in the
present cases has already been decided by the Commission in O.P.Nos.9 & 10
of 2006, and as such the petitioners are precluded from raising the very same
issue once again. Be that as it may, subsequent to the above order of the
Commission, the respondent has consciously entered into PPAs with the petitioners
on 09.06.2006. In terms of the said PPAs, the energy generated from the
projects of the petitioners from COD and delivered to the respondent at the
inter-connection point is liable to be paid for by the respondent at the rate
of Rs.2.70 per unit.
(ii) In the light of the governing provisions of the PPAs, without
conceding to the objection raised by the respondent with respect to the letters
dated 26.02.2005 and 31.03.2005
addressed by the petitioners, the petitioners are entitled for payment of the
energy generated by them from COD i.e., 31.03.2005 till the PPAs were executed.
The relevance or import of letters dated 26.02.2005 and 31.03.2005 on the
subject matter is lost inasmuch as Article 11.7 of PPAs specifically prohibits
to take into consideration any oral or written understanding, representations
or commitments of any kind, expressed or implied, not set forth in the PPAs.
(iii) The allegations of the respondent that the petitioners vide letters
dated 24.06.2006 requested the respondent to process the payment for the energy
generated for future, but not for the energy already generated is totally
incorrect and contrary to contents of the said letters. The respondent is intentionally trying to
avoid the payment for the energy supplied by the petitioners on one pretext or
other.
(iv) The contention of the respondent that claim of the petitioners
is opposed to public interest and as such the principles governing the
contracts between individuals are not applicable is totally misconceived and
contrary to the well established principles of law.
10. On the date of hearing i.e. on 23.06.2007, the counsel for the
petitioners in the both the cases reiterated the identical averments made in
both the petitions and stated that:
(i) Even though PPAs
were entered into between the parties on 09.06.2006, the COD of the projects is
31.03.2005 as defined in Explanation to Article 1.3 of the said PPAs.
(ii) As per Article 2.1 of the PPAs, the petitioners are entitled
for payment for all the delivered energy at the inter-connection point and such
entitlement for price relates back to COD.
(iii) Even though, Issue No. (ii) framed by the Commission in its
common order dated 01.04.2006 in O.P.Nos. 9 & 10 of 2006 relates to payment
for the power pumped into the grid from the generating stations of the
petitioner herein with effect from 31.03.2005, the conclusion arrived at by the
Commission on this issue is relevant for the purpose of arriving at a decision
in the present petitions filed before the Commission. In this regard, it is concluded by the Commission in its order dated 01.04.2006 that “It is
not under dispute that the petitioners have been pumping electricity into the
grid with a clear written commitment that no payments will be claimed for such
energy unless appropriate PPA(s) etc., are entered into. Since, no such PPA(s),
etc., are in place, the Commission finds itself in no position at all to issue
any direction in the matter”. Now
that the petitioners here entered into PPAs, they are entitled for payment for
the goods supplied by them in terms of the said PPAs.
(iv) The contention of the respondent that the
petitioners agreed in writing not to claim money for the energy pumped into the
grid and therefore, they are not entitled for payment prior to 09.06.2006 is
not correct. The said written undertakings have to be looked in the context of
series of letters written by the petitioners, which shows that the respondent
is in a dominant position all along.
Except informing that the petitioners may opt for third party sale as
per the provisions of the Act, subject to payment of wheeling charges and any
such other charges as may be applicable by its letter dated 18.01.2005, the
respondent did not respond to any of the innumerable letters written by the
petitioners.
(v) The contention of the respondent that in
view of the letters dated 26.02.2005 and 31.03.2005, the petitioners are
estopped from claiming for payment for the energy pumped into the grid from
31.03.2005 is not correct. The said letters do not disentitle the petitioners
from receiving payment for the energy pumped into the grid from 31.03.2005. The
claim of the petitioners is based on the terms of the PPAs. The petitioners
either succeed or fail with reference to the definition of COD in the PPAs, but
not with reference to the concessions given through letters. During this
period, the petitioners have been giving one concession or the other to the
respondent, including an undertaking that if the petitioners run their power
plants without PPAs, then all such power generated and pumped into the grid
shall be free of cost.
(vi) The letters dated 26.02.2005 and 31.03.2005 are qualified
letters, wherein the petitioners stated that the generation that is going to be
pumped into the grid will not be claimed for whenever the plant is under
operation without finalizing the PPAs.
The petitioners never stated that they would give the power generated by
them gratuitously. Under general law, unless it is intended to be gratis, the
person who gives goods is entitled for fair cost of such goods.
(vii) The petitioners never intended to give power generated and
pumped to the grid prior to 09.06.2006 gratuitously. Therefore, in accordance with Section 70 of the Indian Contract
Act, 1872, the respondent is bound to pay for such energy delivered to it.
(viii) In its order dated 21.04.2007 in O.P.No.27 of 2004 the
Commission stated that the very fact that the respondents therein received
power from the power plant of the petitioner therein, with or without a valid
PPA, casts a duty on the respondents to compensate for such utilization of
energy.
(ix) Similarly, in its order dated 19.05.2005 in O.P.No.3 of 2007
the Commission rightly held that the validity of the PPA between the parties
therein is valid for 20 years from the COD of the first unit of the project of
the petitioner therein.
(x) The petitioners were
under duress and coercion to write the letters dated 26.02.2005 and 31.03.2005
as per the submissions already made before the Commission in O.P.Nos.9 and 10
of 2006. The petitioners were also under severe pressure to declare the COD as
they did not intend to lose the benefit of depreciation for the financial year
2004-05.
xi) Considering all the
submissions, it is prayed that suitable orders be passed directing the
respondent to pay the petitioners for the power pumped into the grid from the
petitioners’ generating stations with effect from 31.03.2005, up to 08.06.2006.
11. In response, the counsel for the respondent in both the
petitions, reiterated identical replies mentioned in the counters filed on
behalf of the respondent and stated further that
(i) The identical relief sought by the petitioners
herein is verbatim similar to the 2nd relief claimed by the self
same petitioners in O.P.Nos.9 & 10 of 2006. The Commission after carefully
considering the matters therein had not granted any relief for payment of any
amount to the petitioners for the energy pumped into the grid with effect from
31.03.2005. Thus the present petitions are hit by doctrine of res-judicata. Therefore, the petitioners
are precluded from reagitating the same issue once again.
(ii) Article 2.1 of the PPAs states that “All the Delivered Energy at the
interconnection point for sale to APCPDCL will be purchased ……..”.
Thus it is clear whatever energy is delivered ‘for sale’ will be
purchased by the respondent. Similarly,
in Article 2.2, it is stated that “The
Company shall be paid the tariff for the energy delivered at the
interconnection point for sale to APCPDCL ……..”. Likewise Explanation 3 to Article 1.4 also emphasis that payment
will be made for the delivered energy for sale to the respondent.
(iii) Energy is delivered at inter-connection
point for several purposes. Only that energy that is delivered for sale will be
purchased by a licensee, the respondent herein.
(iv) In the letters, both dated 26.02.2005,
the petitioners categorically stated that “We
also state that if we run the power plant without the necessary PPA or wheeling
cum banking agreement in place then all such power that is generated and pumped
into the grid of APTRANSCO during such period shall be free of cost to
APTRANCO” (emphasis supplied). The words ‘such period’ imply the periods
when the PPAs are not in place. Thus it is clear that the period where there is
no PPA, all the power that is pumped into the grid of the respondent shall be
free of cost to it. Therefore, the
question of making payment for the energy pumped, for whatever reason, does not
arise during the absence of the PPAs. The said commitment of the petitioners
will not alter or change after entering into PPAs with the respondent. The
principle of estoppel prohibits the petitioners from claiming payment now.
(v) The letters dated 26.02.2005 and
31.03.2005 clearly show that the petitioners intended to pump energy into the
grid gratuitously. Therefore, Section 70 of the Indian Contract Act, 1872, does
not come to the aid of the petitioners.
(vi) The petitioners induced the respondent to
enter into PPAs on the condition that payment will not be claimed for the
period there is no agreement. Petitioners cannot go back on such inducement and
claim for the payment for the period from 31.03.2005 to 08.06.2006.
(vii) The orders of the Commission relied upon by the petitioners
have no bearing on the cases on hand. The issue in the present cases is totally
different from the issues that arose for consideration before the Commission in
those two matters.
(viii) The letters dated 24.06.2006 and 29.08.2006 of the petitioners
clearly reveal their intention that payment sought therein is not for the
energy already pumped into the grid but to be pumped after entering into the
PPAs.
(ix) For all these reasons, it is prayed that the petitions may be
dismissed.
12. Heard the Counsel for both the parties.
13. It is not out of place here to mention
that the respondent herein had filed separate, but identical, Interlocutory Applications
requesting the Commission to reject the main petitions filed by the petitioners
in O.P.Nos.40 and 41 of 2006 as the same are barred by res-judicata. The said applications were admitted, notices were
issued to the petitioners herein and after hearing the parties concerned, the
Commission passed a common order on 28.03.2007 in I.A.Nos.4 and 5 of 2007
dismissing the said applications for the reasons mentioned therein. However,
the Commission left it open for the respondent herein to raise its objections
with regard to res-judicata in the main petitions.
14. As the common relief claimed by the petitioners in I.A.Nos.2
& 3 of 2007 is coterminous with the main relief claimed in O.P. Nos. 40
&41 of 2006 respectively, the Commission decided to consider both the main
petitions as well as the IAs together to arrive at a decision.
15. The issues that arise for consideration
are --
Issue (i) : Whether
the petitions are barred by the doctrine of res-judicata.
Issue (ii) : Whether
the respondent is liable to pay the petitioners for the power generated and
pumped into the grid from the generating stations of the petitioners from
31.03.2005 to 08.06.2006.
Issue (iii): Whether the petitioners are entitled
for interest at 16% p.a., on the payment for the period from 31.03.2005 to 08.06.2006.
16. Parties are well aware of the earlier
adjudication of dispute by this Commission, also u/s 86(1)(f) of the Act
between the self same parties, and that the common order dated 01.04.2006
passed by the Commission in O.P.Nos.9 and 10 of 2006 attained finality.
Therefore, it is not necessary for the Commission to delve deep into the
details with regard to genesis of the dispute now sought to be raised by the petitioners
herein once again invoking the powers vested in the Commission u/s 86(1)(f)
ibid. It is also not in dispute that
subsequent to passing of the order dated 01.04.2006 referred to above, the
petitioners herein who were also the petitioners in O.P.Nos. 9 and 10 of 2006,
entered into PPAs with the respondent on 09.06.2006, individually.
17. Therefore, the Commission proceeds to
examine the rival contentions on the issues mentioned supra as follows.
Issue (i)
18. The short point that arises for consideration
of the Commission is, whether the entering into PPAs by the petitioners
individually with the respondent on 09.06.2006, a date subsequent to the
passing of the order dated 01.04.2006, confers a fresh cause of action on the
petitioners to seek adjudication with regard to payment for the power generated
and pumped into the grid prior to the date of entering into PPAs. Prima facie,
the common relief claimed by the petitioners is based on the PPAs entered into
by them with the respondent. Apart from the conduct and understanding of the
parties prior to entering into PPAs, it is also contended that the terms of
PPAs which came into existence only on 09.06.2006, require to be examined for
adjudication of the dispute with regard to payment for the power pumped into
the grid with effect from 31.03.2005. Notwithstanding the question whether the
petitioners are entitled for the relief claimed in the present petitions, which
can only be decided on the merits of the cases, the Commission is of the view
that the fact of entering into PPAs between the petitioners with respondent
does confer fresh cause of action on the said parties to seek adjudication by
the Commission u/s 86 (1) (f) of the Act.
19. Earlier the petitioners herein had
invoked the jurisdiction of the Commission requesting it to direct the very
same respondent to purchase electricity from the petitioners and to pay them
for the power pumped into the grid from their generating stations from
31.03.2005 by filing O.P.Nos. 9 and 10 of 2006. Admittedly, at that time, the
parties were not bound by any power purchase agreements between them. After
about two months of the dismissal of the petitions in O.P.Nos.9 and 10 of 2006,
the parties entered into PPAs and the claim of the petitioners for payment as claimed
earlier is based on those PPAs. Therefore, the contention of the respondent
that the present petitions are barred by res-judicata
or that the petitions are not maintainable on the ground of lack of cause of
action, is untenable and cannot be accepted. Had the parties not entered into
PPAs subsequent to disposal of the earlier petitions by the Commission on
01.04.2006 and the present claim of the petitioners were not based on such
agreements, the contention of the respondents that the present petitioners are
barred by res-judicata would have
carried weight. Issue (i) is answered accordingly, and it is held that the
petitions are not hit by the doctrine of
res-judicata and are, therefore, maintainable.
Issue (ii)
20. To consider this issue, first of all, it is necessary to go
into the point raised by the petitioners regarding the applicability of Section
70 of the Indian Contract Act, 1872, which is extracted below:
Section 70 Obligation of person enjoying benefit of non-gratuitous act
“Where a person lawfully does anything for
another person, or delivers anything to him not intending to do so gratuitously
and such other another person enjoys the benefit thereof, the latter is bound
to make compensation to the former in respect of, or to restore, the thing so
done or delivered.”
This Section embodies the
equitable principle of restitution and unjust enrichment.
21. It requires to be examined whether this Section applies
squarely to the facts of the present case.
For the Section to apply, it is a pre-requisite that the petitioners did
not intend to supply power to the respondent gratuitously, and on the other
hand, expected to be paid for it. It is
argued by the respondent that “in view of
the categorical commitment of the petitioner through their letters dated
26.02.2005 and 31.03.2005, that till the PPA came into being, whatever energy
that is pumped into the grid is free of cost to the APTRANSCO” (the
predecessor-in-interest of the respondent herein). The conclusion that can be
drawn from a reading of the above two letters which form part of the record, is
that the stand of the respondents that the petitioners had agreed to pump their
energy into the grid without expecting any payment in return is indeed correct.
The contention of the petitioners, therefore, that Section 70 of the Indian
Contract Act, 1872, applies in this case, cannot be accepted. The two letters mentioned above clearly show
that the petitioner had pumped energy into the grid without expecting to be
paid for it.
22. The other related point to be considered is that of the
alleged duress or coercion under which the petitioner contend, they wrote the
two letters mentioned above. Without going into this issue in detail and
considering the arguments put forward by the petitioners, it requires to be
mentioned here that this issue was dealt with and disposed of in the order of
the Commission dated 01.04.2006 in O.P.Nos.9 and 10 of 2006. No new points or
material has been brought out to the notice of the Commission to persuade it to
modify its conclusion as arrived at in the order dated 01.04.2006 that “……..no evidence is produced in support
of this contention”. Thus, there is no need for the Commission to again go
into this issue, it having already been dealt with and disposed of in the Order
mentioned above.
23. For these reasons, the contention of the petitioners that
Section 70 of the Indian Contract Act, 1872, makes it incumbent on the
respondent to pay for the energy pumped in to the grid by them from dated
31.03.05 to 21.08.06, cannot be accepted.
24. The petitioners’ generating units, being
based on wind power, are NCE (non-conventional energy) projects. The petitioner
claims that the COD of each of the projects is the date on which their first
unit were synchronized with the grid i.e., 31.03.2005, in terms of Article 1.3
of the P.P.A. The date on which the PPAs were entered into i.e., 09.06.2006 is
more than a year subsequent to the date on which the 1st units of
the projects were synchronized with the grid.
The petitioners claim that payment for the energy supplied must be made
from the date of synchronization of their projects with the grid even though
the PPAs were entered into much later.
25. In seeking to understand and deal with this issue, it is
necessary to study the normal practice followed in the electricity industry. In
the natural course of events relating to a generating project that supplies
power to the grid, the PPA is entered into first, and the COD declared
subsequently in accordance with the terms and conditions of the PPA. In this case, the petitioners themselves
approached the respondent requesting the latter to provide grid connectivity.
It is on record, and also admitted by the petitioners, that the respondent
suggested to them that they should try to sell their power to third parties.
However, the petitioners insisted on connecting their projects to the grid and
kept trying to enter into the PPAs with the respondent. The counsel for the
petitioners also stated before the Commission that the petitioners were also
keen not to lose the benefit of depreciation for the financial year 2004-05
which would have been lost if the projects were not connected to the grid by
31.03.2005, (the last day of the financial year) and their COD not declared.
The petitioners were so keen on obtaining grid connectivity and supplying power
to the grid that they told the respondent on more than one occasion that the
power pumped into the grid until the PPAs were entered into, need not be paid
for. Grid connectivity was provided to
them, only after this was agreed to by the petitioners and the PPAs were
executed much later. The conduct of the parties as mentioned above, shows that for obtaining grid connectivity,
in order to subsequently enter into PPAs with the respondent, the petitioners
were quite prepared to supply power to the respondent without being paid for
it.
26. It is true, as submitted by the
petitioners, that according to the
Explanation to Article 1.3 of the PPAs “In
respect of Non-conventional based power projects the date of synchronization of
the first unit of the project will be treated as the Commercial Operation Date
of the project since Ministry of Non-conventional Energy Sources not specified
any guidelines for declaration of the Commercial Operation Date (COD).” However, it does not follow that the COD
in the case of NCE projects can have retrospective operation. The COD is
defined in the PPAs and unless there is a specific clause in the agreement to
the effect that it will have operation from a date prior to the PPAs, it cannot
be a date anterior to the PPAs. On the contrary, the COD has to be determined
in accordance with the agreement between the parties. As discussed earlier, there is no agreement between the parties
that payment would be made for energy supplied prior to the date of the PPAs.
On the other hand, there is a clear commitment on the part of the petitioners
that supply of energy prior to the date of the PPAs shall be free of cost to
the respondent.
27. In this connection, Article 7 of the PPAs which deals with “Duration of agreement” is also
relevant. This clause states that this agreement “…….shall be effective upon its execution and delivery thereof between
parties and shall continue in force from the Commercial Operation Date……..”.
Thus, the agreement becomes operational upon its execution and delivery and not
prior to this “zero-date”. In the present case, this “zero-date” is 09.06.2006. Obviously, the
COD has to be a date subsequent to the signing of the PPAs and cannot be a date
prior to the signing “execution and
delivery” of the PPAs. Such an interpretation is also supported by a
reading of other clauses of the PPAs. For example, Article 5.4 dealing with
Letter of Credit provides that “Not later
than 30 days prior to the Scheduled COD of the first Generating Unit, APCPDCL
shall cause to be in effect an irrevocable revolving Letter of Credit ………”
This too makes it clear that the Letter of Credit has to be opened prior to the
COD, and subsequent to the singing of the PPA. Thus, it is clear that the COD,
in accordance with the practice in the electricity industry, as well as
according to the PPAs, is intended to be
a date subsequent to the execution of the PPAs.
28. In support of the claim of the petitioners, their counsel has
sought to rely on the reasoning given by the Commission in its order dated
19.05.2007 in O.P.No.3/2007. Though the issue relating to COD indeed came up
for discussion in the said Order, the same cannot be applied to the present
case as the issue involved therein was determination of the COD in respect of
the second generating unit (yet to be commissioned) of the same project of the
petitioner therein, and not for treating it for effecting payment for the power
to be generated delivered as is the case in the present petitions. The learned
counsel also referred to the Commission’s Order dated 21.04.2007 in
O.P.No.27/2004. The issue raised in the
petition decided upon in that Order was about payment for the energy
delivered by the petitioner therein, which was pursuant to a direction given by
this Commission on reduction of captive consumption by the petitioner therein
and which was not paid for by the licensee.
Also, in that case there was no commitment on the part of the petitioner
therein to supply energy to the respondents therein gratuitously. Such is not the case here and instead, as
mentioned earlier, the petitioners had made commitments that they would not
claim payment for the energy pumped into the grid by them in the period prior to the date of PPAs. The decisions sought to be invoked by the
petitioners are not relevant to the facts and circumstances of the petitioners
herein.
29. The Commission also finds merit in the contentions of the
respondent that (i) under Article 2.1 of the PPAs, its obligation is to
purchase only that energy that is delivered
“at the interconnection point for sale” (emphasis supplied) to it, and
(ii) Article 2.2 requires the petitioners to be “paid the tariff for energy
delivered at the interconnection point for sale” (emphasis supplied) to
the respondent. And as discussed
earlier, since the petitioners had made a commitment that they would not claim
payment for the energy pumped into the grid prior to the execution of PPAs, the
energy delivered at the respective interconnection points cannot be construed
as having been delivered “for sale”.
30. Thus viewed from any angle, the petitioners are not entitled to
any payment for the power generated and pumped into the grid from their
generating stations during the period from 31.03.2005 to 08.06.2006 and the
Issue (ii) is decided against the petitioners.
Issue(iii)
31. In view of the conclusion as arrived at above in regard to
Issue (ii), the Issue (iii) need not be traversed.
32. For all these reasons, the Commission holds that the
petitioners have failed to make out a case for the grant of any of the reliefs
sought for by them, and accordingly, dismisses the petitions as well as the
IAs.
This Order is corrected and signed
this 9th day of July, 2007.
|
Sd/- |
Sd/- |
Sd/- |
|
(R.RADHA
KISHEN) |
(SURINDER
PAL) |
(K.SWAMINATHAN) |
|
MEMBER |
MEMBER |
CHAIRMAN |
CERTIFIED COPY