ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

Hyderabad

 

Dated: 03-01-2006

 

Present

 

Sri K. Swaminathan, Chairman

Sri. K.Sreerama Murthy, Member

Sri Surinder Pal, Member

 

R. P. No.11 of 2005

 

 

Between 

 

M/s Transmission Corporation of A. P. Limited,

Vidyut Soudha, Somajiguda, Hyderabad.                                 ..             Petitioner

 

 

                                                                        and

 

Nil                                                                                            ..             Respondent

 

 

This petition coming on for hearing on 17-12-2005 in the presence of Sri. P. M. K. Gandhi, Director(RA&CO), and Sri. Santosh Kamat, Consultant,  for the petitioner and having stood over for consideration to this day, the Commission delivered the following:

 
O R D E R

 

 

This is a review petition filed under section 94 of the Electricity Act, 2003, seeking review of the proceedings No.Secy/05, dated 20.09.2005 issued by the Commission approving the Fuel Surcharge Adjustment (hereinafter, the “FSA”) for the period September, 2004 to March, 2005.

 

2.         The following are the averments made in the petition:

 

(a)                The Commission approved an amount of Rs.38.22 crores against the petitioner’s proposal of Rs.148.19 crores towards FSA for the period September, 2004 to March, 2005.

 

(b)               The Commission vide letter No.APERC/Secy/Dir-Engg/DD-Trans/E-511/D.No.1719/2004 dated 06.12.2004 issued interim orders to adopt certain revised technical limits,  as mentioned therein,  for backing down of thermal generating units of Generation Corporation of Andhra Pradesh Limited (APGENCO) with a direction to adopt such technical limits from the date of the order.

 

(c)        FSA amounts for the period mentioned above were computed and submitted by the petitioner as per the technical limits of backing down approved by the Commission for APGENCO’s thermal generating stations.  The Commission is aware that during the day-to-day operation of the grid it is not possible to back down any generating station to zero capacity, and the technical limits of the generating units are given due consideration while resorting to backing down, only to ensure the safety and security of the grid for the benefit of consumers.  As such,  all the costs associated with these limits on backing down need to be borne by the consumers.

 

(d)        If technical limits of backing down were not considered in determination of FSA, the licensees would be subjected to huge financial loss. 

 

(e)          In view of the above, it is prayed that FSA approval for the period  September, 2004 to March, 2005 may be revised.

 

3.         Notice was ordered to the petitioner to substantiate its contentions. 

 

4.         Heard arguments of Sri P.M.K.Gandhi,  Director(RA&CO), and Sri Santosh Kamat,  the Consultant representing the petitioner.

 

5.         The point that arises for consideration is --

            “whether the petitioner is entitled to the relief prayed for”

 

6.         The Commission has prescribed a formula vide the Andhra Pradesh Electricity Regulatory Commission (Conduct of Business) Amendment Regulation No.1 of 2003 for computation of Fuel Surcharge Adjustment. The FSA is based inter-alia on the variations between the variable cost at which the energy is actually purchased and that taken in the Tariff Order, limited, however, to the quantum of energy approved in the Tariff Order. For this purpose, the variable charges of different generating stations, as per the Merit Order determined by their respective variable costs in ascending order, aggregated up to the quantum of energy approved in the Tariff Order are taken into consideration and their weighted average cost is compared with the actual weighted average cost of the energy actually drawn from different stations, up to the Tariff Order quantity.

 

7.         The FSA is an ex-poste allocation of variations in cost – mainly variable – of the Tariff Order–approved volumes of energy. While preferring its review petition, the APTRANSCO has not taken into account the fact that in this scheme of things, the full fixed costs of the generating stations already stand allocated to the consumers of the distribution licensees, through the Tariff Order–approved quantum of energy. Any purchases by the APTRANSCO / distribution licensees over and above this quantum of energy -- for trading and even for increased retail supply to incumbent consumers and the new consumers -- are thus available to APTRANSCO / distribution licensees at variable cost alone i.e. at a much reduced cost, shorn of the fixed costs. APTRANSCO / distribution licensees therefore were put to no undue financial burden due to specification of technical limits for backing down of generating stations of APGENCO vide Commission’s order dated:06.12.2004 referred to above. Accordingly, the Commission has considered it just and appropriate not to allocate to the consumers of the distribution licencees,  the costs, if any,  associated with not being able to  back down  to the extent required according  to the Tariff Order quantities, of  the  generating stations of APGENCO with higher variable cost,  on account of technical limitations  specified in the Commission’s   order dated 6.12.2004.

 

8.      In view of the above, there is no case for review / revision of the FSA as determined in Commission’s proceedings dated 20.09.2005.

 

9.      In the result, the petition is dismissed.

 

The order is corrected and signed on this 3rd day of January, 2006.

 

 

Sd/-

Sd/-

Sd/-

Surinder Pal

K.Sreerama Murthy

K.Swaminathan

MEMBER

MEMBER

CHAIRMAN

 

 

Certified Copy